Data center · Franklin County, Ohio, United States
Cologix COL4
Cologix COL4 is a data center in Franklin County, Ohio, United States, operated by Cologix.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Franklin County, Ohio | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Address | 7500 Alta View Boulevard, Columbus, OH 43085 | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Operator | Cologix | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Building footprint | 8,021 m² (building) | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Coordinates | 40.1184, -82.9993 | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
Research on this data center and its operator.Who owns it up to the parent company, its power supply, grid connection and planning status, and an introduction to the operator.
Request researchHow its operator compares
Cologix operates 6 of the 1,336 data centers in the United States in our data with a named owner; 28 owners have more. Counts cover the data centers in our data that name an owner, holder or operator; an asset with several owners counts for each.
| Operator in United States | Rank | Data centers | Share |
|---|---|---|---|
| Amazon Web Services | 1st | 149 | 11% |
| Digital Realty | 2nd | 87 | 6.5% |
| Microsoft | 3rd | 66 | 4.9% |
| Amazon Data Services Inc. | 4th | 60 | 4.5% |
| 5th | 58 | 4.3% | |
| Cologix | 29th | 6 | 0.45% |
Nearby
Within 50 km of this data center: 8 power plants (2 operating, 1,141 MW) and 4 mines, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Columbus Region Plant | Mine | — | Operating | 21 km |
| Flint | Power plant | 200 MW | Under construction | 23 km |
| Columbus Limestone | Mine | — | Operating | 25 km |
| Columbus Plant | Mine | — | Operating | 25 km |
| Pleasant Prairie Solar Energy LLC | Power plant | 200 MW | Under construction | 26 km |
| Harvey Solar | Power plant | 350 MW | Permitted | 29 km |
Operator and place
More from Cologix
- Cologix ASH1data center
- Cologix COL2data center
- Cologix ASH2data center · under construction
- Cologix Santa Clara SV1 Data Centerdata center
- Cologix COL1data center
Other data centers in Ohio
Data on this page
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI data centers, CC BY 4.0.
- MSHA Mines Data Set. MSHA Mines Data Set, Public domain.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Texas Comptroller qualifying data centers. Texas Comptroller qualifying data centers, Public domain.
- Virginia DEQ issued data center air permits. Virginia DEQ issued data center air permits, Public records.