Google Lancaster is a data center in Ohio, United States, with 137 MW of IT power, owned by Google.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Ohio | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Address | 105 Whiley Rd, Lancaster, OH 43130 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Operating | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Start year | 2024 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Owner | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 | |
| IT power | 137 MW | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Compute (H100 equivalents) | 130,369 H100e | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Capital cost | $5.19 bn | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Chips | TPU v5e, TPU v6e | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 39.7270, -82.6831 | US Census Bureau Geocoder · Public domain · checked 24 Oct 2026 |
Know more about this data center, or want an introduction to its owner? Ask us.
How it compares
Google Lancaster is the 4th-largest of 4 data centers in Ohio and the 36th-largest of 60 in the United States by IT power; its 137 MW is 1.1% of the 11,978 MW we hold for the United States. Ranks and totals cover the data centers in our data that report their IT power, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Ohio | 4th of 4 | 1,244 MW | 11% |
| United States | 36th of 60 | 11,978 MW | 1.1% |
| All data centers in our data | 43rd of 74 | 14,203 MW | 0.96% |
Nearby
Within 50 km of this data center: 5 power plants (1 operating, 564 MW), measured from the coordinates in the facts above. The table shows the nearest 3.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Eastern Cottontail Solar | Power plant | 220 MW | Planned | 21 km |
| Union Ridge Solar | Power plant | 108 MW | Under construction | 29 km |
| Flint | Power plant | 200 MW | Under construction | 41 km |
Owner and place
More from Google
- Google Pryor (North)368 MW
- Google New Albany333 MW
- Google Columbus303 MW
- Google Bristow238 MW
- Google Council Bluffs (East)237 MW
- Google Omaha237 MW
- Google Papillion237 MW
- Google Mesa183 MW
Other data centers in Ohio
- Meta Prometheus471 MW
- Google New Albany333 MW
- Google Columbus303 MW
- Meta Bowling Greenunder construction
- OpenAI Stargate Lordstownunder construction
Data on this page
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI data centers, CC BY 4.0.
- US Census Bureau Geocoder. US Census Bureau Geocoder, Public domain.