RARE CONTEXT Request research

Substation · England, United Kingdom

Townsend Hook 6.6kV Substation

Townsend Hook 6.6kV Substation is a 6.6 kV primary substation in England, United Kingdom, with 2 MVA of demand headroom and 10.5 MVA of generation headroom, operated by South Eastern Power Networks plc (UK Power Networks, South East England licence area).

Map: where Townsend Hook 6.6kV lies
51.3267, 0.4500 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSouth Eastern Power Networks plc (UK Power Networks, South East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom2 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom10.5 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity13.8 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage6.6 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.3267, 0.4500UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 341 power plants (132 operating, 7,508 MW), 326 grid connections (226 operating, 2,630 MW), 57 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Mill Street grid connectionGrid connection6.5 MWOperating0.2 km
Smurfit Kappa Townsend Hook 9933 grid connectionGrid connection40 MWOperating0.2 km
Snodland Paper Mill grid connectionGrid connection1.2 MWOperating0.2 km
Aylesford BESSPower plant29 MWOperating1.4 km
Biossence Solar ParkPower plant4.5 MWOperating2.5 km
Wouldham Road, Wouldham - Battery Storage FacilityPower plant7.5 MWCancelled3.1 km
CXD Infrastructure SolutionsData center——8.6 km
CustodianDC MaidstoneData center——8.6 km
Sota DatacentreData center——19 km

Grid operator and place

Grid connections attached to this substation

More from South Eastern Power Networks plc

Other substations in England

All 2633 substations in England, United Kingdom

Data on this page