Substation · England, United Kingdom

Greyfriars Road 3/4

Greyfriars Road 3/4 is a substation in England, United Kingdom, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Demand headroom0 MVANorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Generation headroom0 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Firm capacity30 MVANorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
LevelPrimaryNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Fed fromDoncaster CentralNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Fed fromWest Melton / Thorpe MarshNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Congestion (offtake)Full (red on the heat map)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Congestion (feed-in)Full (red on the heat map)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage11 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.5261, -1.1391Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this substation and its grid operator.Who owns it up to the parent company, its headroom, congestion and the land around it, and an introduction to the grid operator.

Request research

Nearby

Within 50 km of this substation: 532 power plants (150 operating, 4,457 MW), 514 grid connections (207 operating, 2,245 MW), 8 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Waste 3.8 MW grid connection at Long Lands Lane GenerationGrid connection3.8 MWOperating0.3 km
Solar 3 MW grid connection at Belmont AvenueGrid connection3 MWPlanned0.4 km
Battery storage 50 MW grid connection at Nel Cutts BESS DirectGrid connection50 MWPlanned1.1 km
Cutts Bros, Wharf Road - Battery Storage FacilityPower plant50 MWPermitted1.2 km
Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD)Power plant2 MWOperating1.3 km
Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD) - extensionPower plant3 MWOperating1.3 km
ThalesData center——3.0 km
North Humber to High MarnhamTransmission line—Planned20 km
HSBC Data CentreData center——24 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other substations in England

All 1666 substations in England, United Kingdom