RARE CONTEXT Request research

Substation · England, United Kingdom

Chessington Grid 33kV Substation

Chessington Grid 33kV Substation is a 33 kV primary substation in England, United Kingdom, with 102 MVA of demand headroom and 217 MVA of generation headroom, operated by South Eastern Power Networks plc (UK Power Networks, South East England licence area).

Map: where Chessington Grid 33kV lies
51.3649, -0.2970 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSouth Eastern Power Networks plc (UK Power Networks, South East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom102 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom217 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity229 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.3649, -0.2970UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 330 grid connections (234 operating, 2,111 MW), 324 power plants (115 operating, 3,228 MW), 156 data centers (1 operating, 88 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Digital Realty LHR13Data center——0.6 km
London’s Queen Elizabeth II reservoirPower plant6.3 MWOperating2.9 km
Fair Oak LanePower plant49.9 MWCancelled2.9 km
Rushett Lane grid connectionGrid connection30 MWPlanned3.1 km
Hogsmill Stw grid connectionGrid connection2 MWOperating4.1 km
Kingston Hospital grid connectionGrid connection1 MWOperating5.6 km
Weylands Treatment WorksPower plant6 MWCancelled5.7 km
CapitalLand - CroydenData center——11 km
Segro Croydon (Morgan Stanley)Data center——11 km

Grid operator and place

Grid connections attached to this substation

More from South Eastern Power Networks plc

Other substations in England

All 2633 substations in England, United Kingdom

Data on this page