Basildon Grid 33kV Substation

Basildon Grid 33kV Substation is a 33 kV primary substation in England, United Kingdom, with 65 MVA of demand headroom and 65 MVA of generation headroom, operated by Eastern Power Networks plc (UK Power Networks, East England licence area).

Map: where Basildon Grid 33kV lies
51.5657, 0.4837 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom65 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom65 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity114 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.5657, 0.4837UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 373 power plants (155 operating, 8,459 MW), 362 grid connections (254 operating, 2,874 MW), 57 data centers (1 operating, 88 MW), 1 AI supercomputer and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Marsh Farm (Farm AD)Power plant1.4 MWCancelled1.5 km
Imperium 315Data center——2.3 km
Howard Chase grid connectionGrid connection4.56 MWOperating2.8 km
Basildon STW grid connectionGrid connection1.2 MWOperating2.9 km
Lords Way grid connectionGrid connection20 MWOperating3.0 km
NevendonPower plant10 MWOperating3.3 km
Nevendon Battery Storage ExtensionPower plant5 MWOperating3.3 km
CityFibre CabinetsData center——11 km
Fujitsu Data CentreData center——18 km

Grid operator and place

More from Eastern Power Networks plc

Other substations in England

All 2633 substations in England, United Kingdom

Data on this page