Powered land · Saxony-Anhalt

56 ha site at Gemarkung Knapendorf, Flur 1, Flurstück 5/4

A candidate site of 55.6 ha in Saxony-Anhalt, made up of 1 cadastral parcel, mostly industrial and commercial land. It lies 1.52 km from an unnamed 110 kV substation. The nearest transmission substation, Umspannwerk Lauchstädt (380 kV), is 3 km away, where the grid development plan lists 5 measures.

Owner, grid capacity and planning status on request.We do not publish owners: the German land register (Grundbuch) is not public. Ask us and we find out who owns these parcels, the free capacity at the nearest substation and the zoning that applies, and whether the site is available.

Request owner, grid and planning

Facts

Every value links to its source. Licences and last-checked dates are per row.

FactValueSource
Area55.6 ha (the official areas of its parcels added up)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Cadastral parcels1 (largest: Gemarkung Knapendorf, Flur 1, Flurstück 5/4)ALKIS Sachsen-Anhalt (open cadastre) · dl-de/by-2-0 for LVermGeo open data · checked 24 Oct 2026
Land useIndustrial and commercial land (Industrie- und Gewerbefläche) (100% of the area, as the cadastre records it)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
LocationSaxony-AnhaltRare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Coordinates51.3863, 11.9296 (a point on the largest parcel)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Nearest substation110 kV substation (OSM way/173628971) (1.52 km, site edge to substation fence)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Substation voltage110 kVOpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026
Nearest transmission substationUmspannwerk Lauchstädt (3 km from the nearest parcel, 380 kV, 50Hertz Transmission GmbH)Rare Context powered-land sites · ODbL 1.0 · checked 25 Oct 2026
Planned at that substation380/220 kV grid coupling transformer (2x) (due 2026); STATCOM (2x) (due 2026-2030); MSCDN (2x) (due 2026-2030) (Netzentwicklungsplan; 2 more measures available on request)Netzentwicklungsplan Strom: digital project library · record · CC BY 4.0 · checked 24 Oct 2026

How it compares

#221 of 256 sites in Saxony-Anhalt and #4,273 of 4,863 in Germany by site score. Larger than 32% of the sites in Saxony-Anhalt. Closer to its substation than 31% of them.

PartThis sitePointsOf
Area55.6 ha17.735
Distance to the substation1.52 km8.435
Substation voltage110 kV1030
Site score36100

How the site score works in Germany · Search sites in Saxony-Anhalt

Nearby sites on the same substation

1 other site has this substation as nearest substation and would compete for its capacity.

Data on this page