Powered-land shortlist: Noord-Brabant

A real powered-land shortlist: 20 candidate sites of 10 ha or more next to a high-voltage substation in Noord-Brabant, the Netherlands, outside Natura 2000 areas. Built from public facts only: the grid status of each substation and the owners are in a client's copy, not here.

Order a shortlist for your region.Name the region and what the site is for: size, voltage, use and what to avoid. We reply within 3 working days with the brief. €4,950 per report, excl. VAT.

The brief

A developer of battery storage or a data center is looking for 10 ha or more next to a high-voltage substation in Noord-Brabant, outside Natura 2000 areas, on farmland or land zoned for business.

Filters: 10 ha or more, nearest substation 150 kV or more, outside Natura 2000 areas and zoned agricultural, industrial, commercial and mixed. To print it or save it as a PDF, use your browser's print command: the navigation drops out.

Summary

20 candidate sites in Noord-Brabant, the Netherlands, picked from 715 sites near grid capacity in the province; 305 met the brief. They sit near 12 different substations in 9 municipalities, at most 2 per substation, ranked by the site score.

Land price: arable land €99,160/ha and permanent grassland €91,320/ha on average in 2024 (Eurostat, Noord-Brabant). Farmland prices: land zoned for business sells for more.

#SiteMunicipalityAreaNearest substationGridZoningNatura 2000Owner
1Site at Oploo K 444 and 11 adjacent parcelsLand van Cuijk44.8 ha380 kV Boxmeer, 0.53 kmon requestagricultural (Agrarisch met waarden)6.3 km to MaasduinenOn request
2Site at Roosendaal en Nispen A 3852 and 10 adjacent parcelsRoosendaal49.1 ha150 kV Borchwerf, 0.1 kmon requestagricultural (Agrarisch)8 km to Brabantse WalOn request
3Site at Aarle-Rixtel G 592 and 4 adjacent parcelsLaarbeek45.8 ha150 kV Aarle Rixtel, 0.09 kmon requestagricultural (Agrarisch met waarden - Landschaps- en Natuurwaarden 1)10.2 km to Strabrechtse Heide & BeuvenOn request
4Site at Oud en Nieuw Gastel G 2642 and 10 adjacent parcelsHalderberge49.3 haUnnamed 150 kV substation, 0.19 kmon requestagricultural (Agrarisch met waarden - Landschapswaarden)8 km to Hollands DiepOn request
5Site at Oud en Nieuw Gastel H 2219 and 13 adjacent parcelsHalderberge48.5 haUnnamed 150 kV substation, 0.22 kmon requestagricultural (Agrarisch met waarden - Landschapswaarden)7.9 km to Hollands DiepOn request
6Site at Oploo K 687 and 8 adjacent parcelsLand van Cuijk43.5 ha380 kV Boxmeer, 0.8 kmon requestagricultural (Agrarisch met waarden)6.5 km to MaasduinenOn request
7Site at Cuijk K 3363 and 10 adjacent parcelsLand van Cuijk48.6 ha150 kV Haps, 0.16 kmon requestagricultural (Agrarisch)4.7 km to Oeffelter MeentOn request
8Site at Tilburg F 7255Tilburg48.1 ha380 kV Tilburg, 0.31 kmon requestindustrial (Bedrijf)3 km to Loonse en Drunense Duinen & LeemkuilenOn request
9Site at Tilburg F 7259 and 9 adjacent parcelsTilburg48 ha380 kV Tilburg, 0.09 kmon requestindustrial (Bedrijf)2.3 km to Loonse en Drunense Duinen & LeemkuilenOn request
10Site at Schijndel P 396 and 15 adjacent parcelsMeierijstad37.9 ha150 kV Eerde, 0.16 kmon requestagricultural (Agrarisch met waarden - Kleinschalig landschap)11.9 km to Vlijmens Ven, Moerputten & Bossche BroekOn request
11Site at Oud en Nieuw Gastel G 1371 and 10 adjacent parcelsHalderberge49 haUnnamed 150 kV substation, 0.43 kmon requestagricultural (Agrarisch met waarden - Landschapswaarden)6.6 km to Hollands DiepOn request
12Site at Nuenen C 2885 and 11 adjacent parcelsNuenen, Gerwen en Nederwetten48.4 ha380 kV Eindhoven, 0.55 kmon requestagricultural (Agrarisch met waarden - Groenblauwe mantel)3.6 km to Strabrechtse Heide & BeuvenOn request
13Site at Dinteloord E 563 and 3 adjacent parcelsSteenbergen46.4 ha150 kV Dinteloord, 0.07 kmon requestagricultural (Agrarisch met waarden - Landschapswaarden)4.1 km to Krammer-VolkerakOn request
14Site at Boxmeer W 122 and 13 adjacent parcelsLand van Cuijk42.2 ha150 kV Haps, 0.08 kmon requestagricultural (Agrarisch)4.5 km to Oeffelter MeentOn request
15Site at Schijndel P 337 and 3 adjacent parcelsMeierijstad37 ha150 kV Eerde, 0.23 kmon requestagricultural (Agrarisch met waarden - Natuur en landschap)13.4 km to Vlijmens Ven, Moerputten & Bossche BroekOn request
16Site at Oud en Nieuw Gastel H 338 and 14 adjacent parcelsHalderberge36.3 haUnnamed 150 kV substation, 0.16 kmon requestagricultural (Agrarisch)9.5 km to Hollands DiepOn request
17Site at Standdaarbuiten E 52 and 5 adjacent parcelsMoerdijk36.1 haUnnamed 150 kV substation, 0.18 kmon requestagricultural (Agrarisch)6.7 km to Hollands DiepOn request
18Site at Tilburg F 7242 and 5 adjacent parcelsTilburg46.2 ha150 kV Tilburg West, 0.34 kmon requestindustrial (Bedrijventerrein)4.8 km to Loonse en Drunense Duinen & LeemkuilenOn request
19Site at Aarle-Rixtel G 836 and 7 adjacent parcelsLaarbeek43.7 ha150 kV Aarle Rixtel, 0.35 kmon requestindustrial (Bedrijf - Nutsvoorziening)9.2 km to Strabrechtse Heide & BeuvenOn request
20Site at Dinteloord F 3635 and 6 adjacent parcelsSteenbergen49.7 ha150 kV Dinteloord, 0.13 kmon requestagricultural (Agrarisch met waarden - Landschapswaarden)3.7 km to Krammer-VolkerakOn request

1. Site at Oploo K 444 and 11 adjacent parcels

WhereLand van Cuijk, Noord-Brabant · 51.63478, 5.90191
Area44.8 ha in 12 parcels
Nearest substation380 kV Boxmeer, 0.53 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden) (plan: Buitengebied Sint Anthonis 2013)
Natura 20006.3 km to Maasduinen
Water stresshigh (WRI Aqueduct)
Plants of 50 MW+ within 10 km58 MW solar
Permit notices in the municipality40, latest 16 Oct 2026
OwnerOn request: Kadaster lookup
Site score77 of 100

Events within 5 km since 24 Oct 2024

16, 8 of them on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 6 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.

2. Site at Roosendaal en Nispen A 3852 and 10 adjacent parcels

WhereRoosendaal, Noord-Brabant · 51.55332, 4.44247
Area49.1 ha in 11 parcels
Nearest substation150 kV Borchwerf, 0.1 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch) (plan: Buitengebied Roosendaal Nispen)
Natura 20008 km to Brabantse Wal
Water stresslow (WRI Aqueduct)
Permit notices in the municipality4, latest 16 Oct 2026
OwnerOn request: Kadaster lookup
Site score75 of 100

Events within 5 km since 24 Oct 2024

1, on energy, grid or industry:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • Lies right next to the substation: check that the land is not the grid operator's own or kept for the station's expansion.
  • 9 other candidate sites in the region have the same nearest substation and would compete for its capacity.

3. Site at Aarle-Rixtel G 592 and 4 adjacent parcels

WhereLaarbeek, Noord-Brabant · 51.51882, 5.66754
Area45.8 ha in 5 parcels
Nearest substation150 kV Aarle Rixtel, 0.09 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Landschaps- en Natuurwaarden 1) (plan: Buitengebied)
Natura 200010.2 km to Strabrechtse Heide & Beuven
Water stresshigh (WRI Aqueduct)
Permit notices in the municipality4, latest 31 Aug 2026
OwnerOn request: Kadaster lookup
Site score74 of 100

Events within 5 km since 24 Oct 2024

3, all on energy, grid or industry:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • Lies right next to the substation: check that the land is not the grid operator's own or kept for the station's expansion.
  • 17 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.

4. Site at Oud en Nieuw Gastel G 2642 and 10 adjacent parcels

WhereHalderberge, Noord-Brabant · 51.60161, 4.48818
Area49.3 ha in 11 parcels
Nearest substationUnnamed 150 kV substation, 0.19 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Landschapswaarden) (plan: Eerste herziening bestemmingplan Buitengebied Halderberge)
Natura 20008 km to Hollands Diep
Water stresslow (WRI Aqueduct)
Permit notices in the municipality0
OwnerOn request: Kadaster lookup
Site score73 of 100

Events within 5 km since 24 Oct 2024

None on record.

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 6 other candidate sites in the region have the same nearest substation and would compete for its capacity.

5. Site at Oud en Nieuw Gastel H 2219 and 13 adjacent parcels

WhereHalderberge, Noord-Brabant · 51.59067, 4.49357
Area48.5 ha in 14 parcels
Nearest substationUnnamed 150 kV substation, 0.22 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Landschapswaarden) (plan: Eerste herziening bestemmingplan Buitengebied Halderberge)
Natura 20007.9 km to Hollands Diep
Water stresslow (WRI Aqueduct)
Permit notices in the municipality0
OwnerOn request: Kadaster lookup
Site score73 of 100

Events within 5 km since 24 Oct 2024

None on record.

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 6 other candidate sites in the region have the same nearest substation and would compete for its capacity.

6. Site at Oploo K 687 and 8 adjacent parcels

WhereLand van Cuijk, Noord-Brabant · 51.63029, 5.89315
Area43.5 ha in 9 parcels
Nearest substation380 kV Boxmeer, 0.8 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden) (plan: Buitengebied Sint Anthonis 2013)
Natura 20006.5 km to Maasduinen
Water stresshigh (WRI Aqueduct)
Plants of 50 MW+ within 10 km58 MW solar
Permit notices in the municipality40, latest 16 Oct 2026
OwnerOn request: Kadaster lookup
Site score73 of 100

Events within 5 km since 24 Oct 2024

16, 8 of them on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 6 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.

7. Site at Cuijk K 3363 and 10 adjacent parcels

WhereLand van Cuijk, Noord-Brabant · 51.67570, 5.86660
Area48.6 ha in 11 parcels
Nearest substation150 kV Haps, 0.16 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch) (plan: Buitengebied Cuijk, geconsolideerd)
Natura 20004.7 km to Oeffelter Meent
Water stresshigh (WRI Aqueduct)
Plants of 50 MW+ within 10 km83 MW biomass, 58 MW solar
Permit notices in the municipality40, latest 16 Oct 2026
OwnerOn request: Kadaster lookup
Site score72 of 100

Events within 5 km since 24 Oct 2024

18, 11 of them on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 13 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.

8. Site at Tilburg F 7255

WhereTilburg, Noord-Brabant · 51.60203, 5.05790
Area48.1 ha in 1 parcel
Nearest substation380 kV Tilburg, 0.31 km, operated by TenneT
Grid capacityon request
Zoningindustrial (Bedrijf) (plan: Bedrijventerrein Spinder 2017)
Natura 20003 km to Loonse en Drunense Duinen & Leemkuilen
Water stresshigh (WRI Aqueduct)
Plants of 50 MW+ within 10 km50 MW solar
Permit notices in the municipality13, latest 29 Sept 2026
OwnerOn request: Kadaster lookup
Site score71 of 100

Events within 5 km since 24 Oct 2024

15, all on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned industrial: check what the plan allows on the plot itself.
  • 11 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.
  • 3 battery storage or data center permits and plans within 5 km since 1 Apr 2025: others want grid capacity here too.

9. Site at Tilburg F 7259 and 9 adjacent parcels

WhereTilburg, Noord-Brabant · 51.60636, 5.05505
Area48 ha in 10 parcels
Nearest substation380 kV Tilburg, 0.09 km, operated by TenneT
Grid capacityon request
Zoningindustrial (Bedrijf) (plan: Bedrijventerrein Spinder 2017)
Natura 20002.3 km to Loonse en Drunense Duinen & Leemkuilen
Water stresshigh (WRI Aqueduct)
Plants of 50 MW+ within 10 km50 MW solar
Permit notices in the municipality13, latest 29 Sept 2026
OwnerOn request: Kadaster lookup
Site score71 of 100

Events within 5 km since 24 Oct 2024

15, all on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned industrial: check what the plan allows on the plot itself.
  • Lies right next to the substation: check that the land is not the grid operator's own or kept for the station's expansion.
  • 11 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Natura 2000 area Loonse en Drunense Duinen & Leemkuilen lies 2.3 km away: nitrogen deposition from building and running the site needs an AERIUS calculation. The AERIUS register shows 4 mol/yr of nitrogen space available there.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.
  • 3 battery storage or data center permits and plans within 5 km since 1 Apr 2025: others want grid capacity here too.

10. Site at Schijndel P 396 and 15 adjacent parcels

WhereMeierijstad, Noord-Brabant · 51.61036, 5.48099
Area37.9 ha in 16 parcels
Nearest substation150 kV Eerde, 0.16 km
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Kleinschalig landschap) (plan: Landelijk gebied)
Natura 200011.9 km to Vlijmens Ven, Moerputten & Bossche Broek
Water stresshigh (WRI Aqueduct)
Permit notices in the municipality13, latest 12 Aug 2026
OwnerOn request: Kadaster lookup
Site score71 of 100

Events within 5 km since 24 Oct 2024

8, all on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 13 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.
  • 4 battery storage or data center permits and plans within 5 km since 31 Oct 2025: others want grid capacity here too.

11. Site at Oud en Nieuw Gastel G 1371 and 10 adjacent parcels

WhereHalderberge, Noord-Brabant · 51.61604, 4.48989
Area49 ha in 11 parcels
Nearest substationUnnamed 150 kV substation, 0.43 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Landschapswaarden) (plan: Eerste herziening bestemmingplan Buitengebied Halderberge)
Natura 20006.6 km to Hollands Diep
Water stresslow (WRI Aqueduct)
Permit notices in the municipality0
OwnerOn request: Kadaster lookup
Site score70 of 100

Events within 5 km since 24 Oct 2024

None on record.

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 9 other candidate sites in the region have the same nearest substation and would compete for its capacity.

12. Site at Nuenen C 2885 and 11 adjacent parcels

WhereNuenen, Gerwen en Nederwetten, Noord-Brabant · 51.44197, 5.54869
Area48.4 ha in 12 parcels
Nearest substation380 kV Eindhoven, 0.55 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Groenblauwe mantel) (plan: Buitengebied Nuenen)
Natura 20003.6 km to Strabrechtse Heide & Beuven
Water stresshigh (WRI Aqueduct)
Permit notices in the municipality0
OwnerOn request: Kadaster lookup
Site score70 of 100

Events within 5 km since 24 Oct 2024

6, all on energy, grid or industry:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 8 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.

13. Site at Dinteloord E 563 and 3 adjacent parcels

WhereSteenbergen, Noord-Brabant · 51.61579, 4.39245
Area46.4 ha in 4 parcels
Nearest substation150 kV Dinteloord, 0.07 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Landschapswaarden) (plan: Buitengebied Dinteloord en Prinsenland)
Natura 20004.1 km to Krammer-Volkerak
Water stresslow (WRI Aqueduct)
Permit notices in the municipality3, latest 25 Jun 2026
OwnerOn request: Kadaster lookup
Site score70 of 100

Events within 5 km since 24 Oct 2024

1, on energy, grid or industry:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • Lies right next to the substation: check that the land is not the grid operator's own or kept for the station's expansion.
  • 25 other candidate sites in the region have the same nearest substation and would compete for its capacity.

14. Site at Boxmeer W 122 and 13 adjacent parcels

WhereLand van Cuijk, Noord-Brabant · 51.67671, 5.88849
Area42.2 ha in 14 parcels
Nearest substation150 kV Haps, 0.08 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch) (plan: Veegplan Buitengebied 2018)
Natura 20004.5 km to Oeffelter Meent
Water stresshigh (WRI Aqueduct)
Plants of 50 MW+ within 10 km83 MW biomass, 58 MW solar
Permit notices in the municipality40, latest 16 Oct 2026
OwnerOn request: Kadaster lookup
Site score70 of 100

Events within 5 km since 24 Oct 2024

18, 13 of them on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • Lies right next to the substation: check that the land is not the grid operator's own or kept for the station's expansion.
  • 13 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.

15. Site at Schijndel P 337 and 3 adjacent parcels

WhereMeierijstad, Noord-Brabant · 51.61224, 5.49128
Area37 ha in 4 parcels
Nearest substation150 kV Eerde, 0.23 km
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Natuur en landschap) (plan: Landelijk gebied)
Natura 200013.4 km to Vlijmens Ven, Moerputten & Bossche Broek
Water stresshigh (WRI Aqueduct)
Permit notices in the municipality13, latest 12 Aug 2026
OwnerOn request: Kadaster lookup
Site score70 of 100

Events within 5 km since 24 Oct 2024

7, all on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 13 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.
  • 4 battery storage or data center permits and plans within 5 km since 31 Oct 2025: others want grid capacity here too.

16. Site at Oud en Nieuw Gastel H 338 and 14 adjacent parcels

WhereHalderberge, Noord-Brabant · 51.58877, 4.48797
Area36.3 ha in 15 parcels
Nearest substationUnnamed 150 kV substation, 0.16 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch) (plan: Eerste herziening bestemmingplan Buitengebied Halderberge)
Natura 20009.5 km to Hollands Diep
Water stresslow (WRI Aqueduct)
Permit notices in the municipality0
OwnerOn request: Kadaster lookup
Site score70 of 100

Events within 5 km since 24 Oct 2024

None on record.

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 4 other candidate sites in the region have the same nearest substation and would compete for its capacity.

17. Site at Standdaarbuiten E 52 and 5 adjacent parcels

WhereMoerdijk, Noord-Brabant · 51.60890, 4.50536
Area36.1 ha in 6 parcels
Nearest substationUnnamed 150 kV substation, 0.18 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch) (plan: Buitengebied Moerdijk)
Natura 20006.7 km to Hollands Diep
Water stresslow (WRI Aqueduct)
Permit notices in the municipality0
OwnerOn request: Kadaster lookup
Site score70 of 100

Events within 5 km since 24 Oct 2024

None on record.

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • 9 other candidate sites in the region have the same nearest substation and would compete for its capacity.

18. Site at Tilburg F 7242 and 5 adjacent parcels

WhereTilburg, Noord-Brabant · 51.59601, 5.01732
Area46.2 ha in 6 parcels
Nearest substation150 kV Tilburg West, 0.34 km, operated by TenneT
Grid capacityon request
Zoningindustrial (Bedrijventerrein) (plan: Bedrijventerrein Vossenberg 2008)
Natura 20004.8 km to Loonse en Drunense Duinen & Leemkuilen
Water stresshigh (WRI Aqueduct)
Plants of 50 MW+ within 10 km50 MW solar
Permit notices in the municipality13, latest 29 Sept 2026
OwnerOn request: Kadaster lookup
Site score69 of 100

Events within 5 km since 24 Oct 2024

14, all on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned industrial: check what the plan allows on the plot itself.
  • 18 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.
  • 2 battery storage or data center permits and plans within 5 km since 7 Jul 2025: others want grid capacity here too.

19. Site at Aarle-Rixtel G 836 and 7 adjacent parcels

WhereLaarbeek, Noord-Brabant · 51.50729, 5.66370
Area43.7 ha in 8 parcels
Nearest substation150 kV Aarle Rixtel, 0.35 km, operated by TenneT
Grid capacityon request
Zoningindustrial (Bedrijf - Nutsvoorziening) (plan: Buitengebied - 1e herziening)
Natura 20009.2 km to Strabrechtse Heide & Beuven
Water stresshigh (WRI Aqueduct)
Permit notices in the municipality4, latest 31 Aug 2026
OwnerOn request: Kadaster lookup
Site score69 of 100

Events within 5 km since 24 Oct 2024

11, all on energy, grid or industry; 6 below, those first, newest first:

What to check

  • Zoned industrial: check what the plan allows on the plot itself.
  • 17 other candidate sites in the region have the same nearest substation and would compete for its capacity.
  • Baseline water stress is high in this river basin (WRI Aqueduct): a water-cooled load would compete for water.
  • 5 battery storage or data center permits and plans within 5 km since 16 Jan 2025: others want grid capacity here too.

20. Site at Dinteloord F 3635 and 6 adjacent parcels

WhereSteenbergen, Noord-Brabant · 51.61700, 4.38080
Area49.7 ha in 7 parcels
Nearest substation150 kV Dinteloord, 0.13 km, operated by TenneT
Grid capacityon request
Zoningagricultural (Agrarisch met waarden - Landschapswaarden) (plan: Buitengebied Dinteloord en Prinsenland)
Natura 20003.7 km to Krammer-Volkerak
Water stresslow (WRI Aqueduct)
Permit notices in the municipality3, latest 25 Jun 2026
OwnerOn request: Kadaster lookup
Site score68 of 100

Events within 5 km since 24 Oct 2024

1, on energy, grid or industry:

What to check

  • Zoned agricultural: a battery, data center or industrial use needs a change to the omgevingsplan or a permit for an activity outside it.
  • Lies right next to the substation: check that the land is not the grid operator's own or kept for the station's expansion.
  • 25 other candidate sites in the region have the same nearest substation and would compete for its capacity.

How this list was made

Every site comes from the Rare Context site model: cadastral parcels, alone or merged with adjacent ones, within 2 km of a substation of 110 kV or more, plus business parks with land for sale. The query kept the sites that met the brief, ranked them by the site score (area, distance to the substation, its voltage and distance to Natura 2000), and took the best, at most 2 per substation.

Grid capacity is what the grid operators publish for the nearest substation: in the Netherlands a congestion status per station for offtake and feed-in, from the capacity map of Netbeheer Nederland, matched to the substation by name and voltage. We may not republish those statuses, so this sample shows them as on request, and ranks on public facts only. A client copy shows the status of each site and its ranking weighs it, so sites at a full substation move down the list.

Events are permit notices, planning decisions, connection queue entries and owners' announcements on records within 5 km of the site, from the last 24 months.

Owners: We buy the Kadaster's owner record (BRK eigendomsinformatie) for each parcel of the shortlisted sites only, never in bulk. In this sample they are left out.

Sources

Research from public registers and open data, as of the date above. It is not investment advice, a valuation or an offer: Rare Context does not recommend buying or selling any asset or share and does not negotiate for anyone. Check every fact with its source before acting on it.