Maerdy

Maerdy is a power plant in Rhondda Cynon Taf, Wales, United Kingdom, with 24 MW of capacity, operated by Greencoat UK Wind.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRhondda Cynon Taf (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Addressland NW of Maerdy and NE of Treherbert, Rhigos, CF44 9UFDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2013DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date10 Feb 2008 (permit 11/0198/10, Town and Country Planning Act, issued by Rhondda Cynon Taf)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date1 Sept 2006 (reference 11/0198/10, planning authority Rhondda Cynon Taf)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 Feb 2008 (granted, reference 11/0198/10, planning authority Rhondda Cynon Taf)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorGreencoat UK WindDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity24 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units8 units (3 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.6983, -3.5155DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Maerdy is the 61st-largest of 424 power plants in Wales and the 933rd-largest of 5,050 in the United Kingdom by capacity; its 24 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales61st of 4249,068 MW0.26%
United Kingdom933rd of 5,050115,642 MW<0.1%
All power plants in our data3,368th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 11/0198/10
  2. Started operating

Nearby

Within 50 km of this power plant: 212 grid connections and 6 data centers, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Abergorki Wind Farm grid connectionGrid connection——2.6 km
Rhondda Cynon TAF Maerdy Windfarm grid connectionGrid connection——2.6 km
CF44 9UG, BRYNGOLWG Solar Farm, Rhigos grid connectionGrid connection——5.1 km
Centerprise International (Distribution)Data center——21 km
CGI DatacenterData center——23 km
Centerprise International NewportData center——37 km

Operator and place

More from Greencoat UK Wind

Other power plants in Wales

All 616 power plants in Wales, United Kingdom

Data on this page