Power plant · Aberdeenshire, Scotland, United Kingdom

Woodlands Farm - Elion

Woodlands Farm - Elion is a cancelled wind power plant in Aberdeenshire, Scotland, United Kingdom, with 2.3 MW of capacity, operated by Scotfarms Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAberdeenshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressUdny, Ellon, Grampian, AB41 6SPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (appeal refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date4 Dec 2008 (reference APP/2008/4051, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date29 Jun 2015 (refused, reference APP/2008/4051, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date25 Jun 2010 (appeal refused, reference APP/2008/4051, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorScotfarms Ltd (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.3 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units1 units (2.3 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.3059, -2.2003DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority Aberdeenshire, reference APP/2008/4051)
  2. Permit refused (appeal refused, planning authority Aberdeenshire, reference APP/2008/4051)
  3. Permit applied for (planning authority Aberdeenshire, reference APP/2008/4051)

How it compares

Woodlands Farm - Elion is the 1,084th-largest of 1,340 power plants in Scotland and the 4,694th-largest of 5,834 in the United Kingdom by capacity; its 2.3 MW is <0.1% of the 200,500 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland1,084th of 1,34046,467 MW<0.1%
United Kingdom4,694th of 5,834200,500 MW<0.1%
All power plants in our data13,826th of 15,7991,918,113 MW<0.1%

Nearby

Within 50 km of this power plant: 145 grid connections (63 operating, 475 MW), 78 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Udny Community grid connectionGrid connection1.07 MWOperating1.7 km
Kingseat PrimarySubstation——4.5 km
Cairnbrogie Wind Farm grid connectionGrid connection4.1 MWPlanned5.0 km
Cairnbrogie Wind Farm grid connectionGrid connection4.5 MWPlanned5.0 km
Oldmeldrum PrimarySubstation——7.2 km
Balmedie PrimarySubstation——9.2 km
BrightsolidData center——17 km

Operator and place

Other power plants in Scotland

All 2105 power plants in Scotland, United Kingdom