Power plant · West Lothian, Scotland, United Kingdom
Trinlaymire Farm - Solar farm, Battery storage
Trinlaymire Farm - Solar farm, Battery storage is a permitted solar power plant in West Lothian, Scotland, United Kingdom, with 29.9 MW of capacity, operated by Trinlaymire Net Zero Solar Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | West Lothian (coordinates), Scotland | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Trinlaymire Farm Threemiletown Linlithgow, EH49 6NF | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 20 Dec 2024 (permit 0568/FUL/24, Town and Country Planning Act, issued by West Lothian) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 23 Aug 2024 (reference 0568/FUL/24, planning authority West Lothian) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 20 Dec 2024 (granted, reference 0568/FUL/24, planning authority West Lothian) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Trinlaymire Net Zero Solar Limited (applicant) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 29.9 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 60.8 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 55.9666, -3.5025 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Permit granted (planning authority West Lothian, reference 0568/FUL/24)
- Permit applied for (planning authority West Lothian, reference 0568/FUL/24)
How it compares
Trinlaymire Farm - Solar farm, Battery storage is the 466th-largest of 742 power plants planned, permitted or under construction in Scotland and the 1,409th-largest of 2,548 in the United Kingdom by capacity; its 29.9 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| Scotland | 466th of 742 | 93,216 MW | <0.1% |
| United Kingdom | 1,409th of 2,548 | 279,068 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 2,855th of 5,799 | 657,076 MW | <0.1% |
Nearby
Within 50 km of this power plant: 37 grid connections (13 operating, 189 MW), 16 substations and 13 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Edinburgh SC-3 | Data center | — | — | 7.1 km |
| Sungard Availability Services | Data center | — | — | 10 km |
| Edinburgh SC-2 | Data center | — | — | 14 km |
| Glendevon Primary | Substation | — | — | 28 km |
| Milnathort Primary | Substation | — | — | 30 km |
| Shire End 20MW PV grid connection | Grid connection | 20 MW | Planned | 34 km |
| Windburn Wind Farm 75MW Wind, 35MW BESS grid connection | Grid connection | 110 MW | Planned | 36 km |
| Highland Spring Group grid connection | Grid connection | 5.5 MW | Planned | 37 km |
| Dunblane Primary | Substation | — | — | 38 km |
Operator and place
Other power plants in Scotland
- Longannet2,260 MW
- Torness1,200 MW
- Peterhead1,180 MW
- Seagreen1,075 MW
- Hunterston B985 MW
- Moray East950 MW
- Moray West Offshore Wind Farm Project882 MW
- Auchentiber Road - Battery Energy Storage System700 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.
- Wikidata. Wikidata, CC0 1.0.