Power plant · Moray, Scotland, United Kingdom

The Portgordon Maltings, Phase 2 - Aerobic Digestion Facility

The Portgordon Maltings, Phase 2 - Aerobic Digestion Facility is a permitted power plant in Moray, Scotland, United Kingdom, with 4 MW of capacity, operated by Grisasan Engineering Services Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMoray (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Address150 Metres To The W/O The Portgordon, Maltings, Buckie, AB56 5BUDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date13 Mar 2024 (permit 23/00894/APP, Town and Country Planning Act, issued by Moray)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date6 Jun 2023 (reference 23/00894/APP, planning authority Moray)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date13 Mar 2024 (granted, reference 23/00894/APP, planning authority Moray)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorGrisasan Engineering Services LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity4 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyAnaerobic DigestionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.6578, -3.0235DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Moray, reference 23/00894/APP)
  2. Permit applied for (planning authority Moray, reference 23/00894/APP)

How it compares

The Portgordon Maltings, Phase 2 - Aerobic Digestion Facility is the 772nd-largest of 872 power plants planned, permitted or under construction in Scotland and the 2,616th-largest of 3,222 in the United Kingdom by capacity; its 4 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland772nd of 87299,272 MW<0.1%
United Kingdom2,616th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data5,764th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 85 grid connections (41 operating, 456 MW) and 37 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Buckie PrimarySubstation——4.4 km
Boormalt 2.3MW PV grid connectionGrid connection2.3 MWPlanned5.2 km
Fochabers PrimarySubstation——6.5 km
Auchinderran Wind Farm grid connectionGrid connection31 MWPlanned8.6 km
Lhanbryde PrimarySubstation——11 km
Netherton of Windyhills grid connectionGrid connection4.37 MWOperating12 km

Operator and place

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page