Power plant · Shetland Islands, Scotland, United Kingdom

North Hoo Fields Wind Farm

North Hoo Fields Wind Farm is a permitted wind power plant in Shetland Islands, Scotland, United Kingdom, with 2.3 MW of capacity, operated by North Fish.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationShetland Islands (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressNorth Hoo Fields, Gremista, Lerwick, Shetland, Shetland Isles, ZE1DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date11 Jul 2024 (permit 2023/275/PPF, Town and Country Planning Act, issued by Shetland Islands)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date27 Nov 2023 (reference 2023/275/PPF, planning authority Shetland Islands)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date11 Jul 2024 (granted, reference 2023/275/PPF, planning authority Shetland Islands)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNorth Fish (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.3 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units1 units (2.3 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates60.1689, -1.1801DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Shetland Islands, reference 2023/275/PPF)
  2. Permit applied for (planning authority Shetland Islands, reference 2023/275/PPF)

How it compares

North Hoo Fields is the 702nd-largest of 742 power plants planned, permitted or under construction in Scotland and the 2,239th-largest of 2,548 in the United Kingdom by capacity; its 2.3 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland702nd of 74293,216 MW<0.1%
United Kingdom2,239th of 2,548279,068 MW<0.1%
All power plants planned, permitted or under construction in our data5,443rd of 5,799657,076 MW<0.1%

Nearby

Within 50 km of this power plant: 24 grid connections (17 operating, 81.1 MW) and 10 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
North HOO Field Ltd grid connectionGrid connection2.3 MWPlanned0.6 km
North Fish (Shetland) Ltd grid connectionGrid connection2.3 MWPlanned0.7 km
Zenobe Shetland Backup BESS grid connectionGrid connection99.7 MWPlanned0.8 km
Shetland / GremistaSubstation——0.9 km
Lerwick PrimarySubstation——0.9 km
Scalloway PrimarySubstation——5.4 km

Operator and place

Other power plants in Scotland

All 2105 power plants in Scotland, United Kingdom

Data on this page