Power plant · East Lothian, Scotland, United Kingdom
Millerhill AD (Waste AD)
Millerhill AD (Waste AD) is a power plant in East Lothian, Scotland, United Kingdom, with 1.5 MW of capacity, operated by Aluana Renewable Energy) and Ancala Bioenergy.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | East Lothian (coordinates), Scotland | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Former Millerhill Marshalling Yards Whitehill Mains Road Millerhill Dalkeith, EH11 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2016 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 31 May 2013 (permit 13/00077/MSC, Town and Country Planning Act, issued by Midlothian) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 25 Jan 2013 (reference 13/00077/MSC, planning authority Midlothian) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 31 May 2013 (granted, reference 13/00077/MSC, planning authority Midlothian) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Aluana Renewable Energy) (Ancala Bioenergy (formerly Biogen/Aluana Renewable Energy)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Ancala Bioenergy (Ancala Bioenergy (formerly Biogen/Aluana Renewable Energy)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 1.5 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Anaerobic Digestion | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 55.9269, -3.0805 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Commissioned
- Permit granted (planning authority Midlothian, reference 13/00077/MSC)
- Permit applied for (planning authority Midlothian, reference 13/00077/MSC)
How it compares
Millerhill AD (Waste AD) is the 1,096th-largest of 1,196 power plants in Scotland and the 4,531st-largest of 5,050 in the United Kingdom by capacity; its 1.5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| Scotland | 1,096th of 1,196 | 34,589 MW | <0.1% |
| United Kingdom | 4,531st of 5,050 | 115,622 MW | <0.1% |
| All power plants in our data | 11,084th of 12,032 | 1,190,447 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Started operating
Nearby
Within 50 km of this power plant: 18 grid connections (6 operating, 87 MW), 9 data centers and 4 substations, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| RBS Melville Gate Data Centre | Data center | — | — | 3.6 km |
| Data center, Scotland (OSM way 1548060501) | Data center | — | — | 11 km |
| RBS Data Centre | Data center | — | — | 11 km |
| Milnathort Primary | Substation | — | — | 40 km |
| Binn Farm Glenfarg grid connection | Grid connection | 30 MW | Planned | 42 km |
| Shire End 20MW PV grid connection | Grid connection | 20 MW | Planned | 45 km |
| Fragland grid connection | Grid connection | 120 MW | Planned | 45 km |
| Glendevon Primary | Substation | — | — | 45 km |
| Abernethy GSP | Substation | — | — | 48 km |
Operators and place
Other power plants in Scotland
- Seagreen1,075 MW
- Moray East950 MW
- Moray West Offshore Wind Farm Project882 MW
- Lewis Wind Farm (Barvas Moor)652 MW
- Beatrice588 MW
- Neart na Gaoithe450 MW
- Viking Wind Farm443 MW
- Cruachan440 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- JRC Open Power Plants Database (JRC-PPDB-OPEN), European Commission, Joint Research Centre. JRC Open Power Plants Database (JRC-PPDB-OPEN), CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Dutch power station owners' and operators' pages. Dutch power station owners' and operators' pages, Facts only, each linked to its page.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.