Power plant · Fife, Scotland, United Kingdom

Markinch Biomass CHP Plant

Markinch Biomass CHP Plant is a power plant in Fife, Scotland, United Kingdom, with 65 MW of capacity, operated by RWE.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationFife (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressMarkinch, FifeDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2014DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date1 Jul 2008 (Electricity Act 1989 section 36, issued by Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date1 Aug 2005 (planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date1 Jul 2008 (granted, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorRWEDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity65 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBiomass (dedicated)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.2027, -3.1594DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Scottish Government (S36))
  3. Permit applied for (planning authority Scottish Government (S36))

How it compares

Markinch Biomass CHP Plant is the 105th-largest of 1,196 power plants in Scotland and the 248th-largest of 5,050 in the United Kingdom by capacity; its 65 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland105th of 1,19634,589 MW0.19%
United Kingdom248th of 5,050115,622 MW<0.1%
All power plants in our data1,537th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 71 grid connections (23 operating, 384 MW), 51 substations and 9 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Binn Farm Glenfarg grid connectionGrid connection30 MWPlanned12 km
Binn Farm Wind Farm grid connectionGrid connection6.7 MWOperating16 km
Binn Farm - Wind grid connectionGrid connection9.9 MWPlanned16 km
Milnathort PrimarySubstation——17 km
Abernethy GSPSubstation——17 km
Abernethy PrimarySubstation——17 km
Data center, Scotland (OSM way 1548060501)Data center——31 km
Pulsant Edinburgh SC-1Data center——31 km
Pulsant Edinburgh South Gyle SC-1Data center——31 km

Operator and place

More from RWE

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page