Power plant · Fife, Scotland, United Kingdom

Lochhead Landfill CHP

Lochhead Landfill CHP is a power plant in Fife, Scotland, United Kingdom, with 1.7 MW of capacity, operated by Fife Council.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationFife (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressDunfermline,DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2014DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date18 Aug 2011 (permit 11/01206/FULL, Town and Country Planning Act, issued by Fife)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date7 Mar 2011 (reference 11/01206/FULL, planning authority Fife)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date18 Aug 2011 (granted, reference 11/01206/FULL, planning authority Fife)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorFife CouncilDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.7 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyAnaerobic DigestionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.0984, -3.4667DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Fife, reference 11/01206/FULL)
  3. Permit applied for (planning authority Fife, reference 11/01206/FULL)

How it compares

Lochhead Landfill CHP is the 1,190th-largest of 1,326 power plants in Scotland and the 5,020th-largest of 5,723 in the United Kingdom by capacity; its 1.7 MW is <0.1% of the 136,106 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland1,190th of 1,32640,645 MW<0.1%
United Kingdom5,020th of 5,723136,106 MW<0.1%
All power plants in our data11,445th of 12,7051,210,931 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 50 grid connections (16 operating, 243 MW), 31 substations and 10 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Milnathort PrimarySubstation——15 km
Glendevon PrimarySubstation——15 km
Shire End 20MW PV grid connectionGrid connection20 MWPlanned19 km
Edinburgh SC-3Data center——19 km
Pulsant Edinburgh SC-1Data center——22 km
Pulsant Edinburgh South Gyle SC-1Data center——22 km
Lochebank Windfarm grid connectionGrid connection9.45 MWOperating23 km
Fragland grid connectionGrid connection120 MWPlanned23 km
Gleneagles PrimarySubstation——27 km

Operator and place

More from Fife Council

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page