Power plant · Aberdeenshire, Scotland, United Kingdom

Greystone, Blackhills - Battery Energy Storage System

Greystone, Blackhills - Battery Energy Storage System is a planned power plant in Aberdeenshire, Scotland, United Kingdom, with 500 MW of capacity, operated by Peterhead Flexpower.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAberdeenshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressThe W/O Greystone, Blackhills, Peterhead, AB42 3JPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date4 Jul 2025 (reference ECU00006204, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorPeterhead FlexpowerDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity500 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.4765, -1.8443DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit applied for (planning authority Scottish Government (S36), reference ECU00006204)

How it compares

Greystone, Blackhills - Battery Energy Storage System is the 35th-largest of 872 power plants planned, permitted or under construction in Scotland and the 107th-largest of 3,222 in the United Kingdom by capacity; its 500 MW is 0.17% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland35th of 87299,272 MW0.5%
United Kingdom107th of 3,222300,461 MW0.17%
All power plants planned, permitted or under construction in our data249th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 101 grid connections (44 operating, 253 MW), 64 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Blackhills Farm grid connectionGrid connection6.56 MWOperating1.3 km
Wells Forest Farm 25MW grid connectionGrid connection50.2 MWPlanned1.4 km
Stoneyhill Landfill grid connectionGrid connection1.94 MWOperating2.1 km
Stoneyhill PrimarySubstation——2.5 km
Peterhead Shell GSPSubstation——2.6 km
Boddam PrimarySubstation——2.8 km
BrightsolidData center——41 km

Operator and place

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom