Flatterton Farm, Flatterton Road - Battery Storage is a permitted power plant in Inverclyde, Scotland, United Kingdom, with 49.9 MW of capacity, operated by Big Battery Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Inverclyde (coordinates), Scotland | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Flatterton Farm, Flatterton Road, Greenock, PA16 0AD | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 5 Jun 2024 (permit 23/0205/IC, Town and Country Planning Act, issued by Inverclyde) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 9 Oct 2023 (reference 23/0205/IC, planning authority Inverclyde) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 5 Jun 2024 (granted, reference 23/0205/IC, planning authority Inverclyde) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Big Battery Limited (Big Battery (Flatterton Farm) Limited) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 49.9 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery (stand-alone storage) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 55.9336, -4.8363 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Permit granted (planning authority Inverclyde, reference 23/0205/IC)
- Permit applied for (planning authority Inverclyde, reference 23/0205/IC)
How it compares
Flatterton Farm, Flatterton Road - Battery Storage is the 320th-largest of 872 power plants planned, permitted or under construction in Scotland and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| Scotland | 320th of 872 | 99,272 MW | <0.1% |
| United Kingdom | 886th of 3,222 | 300,461 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 1,966th of 6,455 | 664,040 MW | <0.1% |
Nearby
Within 50 km of this power plant: 38 substations, 26 grid connections (17 operating, 258 MW) and 4 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Dunoon Primary | Substation | — | — | 6.4 km |
| Dunoon GSP | Substation | — | — | 8.4 km |
| 45MW Battery grid connection | Grid connection | 52.7 MW | Planned | 8.4 km |
| Innellan Primary | Substation | — | — | 8.7 km |
| Auchencarroch Energy Ltd grid connection | Grid connection | 3.04 MW | Operating | 18 km |
| Auchincarroch (GEN464G2) grid connection | Grid connection | 1.01 MW | Operating | 18 km |
| iomart Glasgow Data Centre | Data center | — | — | 36 km |
| Verizon Glasgow GLSGGB | Data center | — | — | 36 km |
| DataVita DV2 | Data center | — | — | 37 km |
Operator and place
More from Big Battery Limited
- Holmquarry Road - Battery Storage60.4 MW · permitted
- Cornhills Farm, Muttonhole Road - Battery Storage49.9 MW · permitted
Other power plants in Scotland
- Seagreen1,075 MW
- Moray East950 MW
- Moray West Offshore Wind Farm Project882 MW
- Lewis Wind Farm (Barvas Moor)652 MW
- Beatrice588 MW
- Neart na Gaoithe450 MW
- Viking Wind Farm443 MW
- Cruachan440 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.