Power plant · North Ayrshire, Scotland, United Kingdom

Castlehill Solar Farm

Castlehill Solar Farm is a cancelled power plant in North Ayrshire, Scotland, United Kingdom, with 5 MW of capacity, operated by SBC Renewables.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNorth Ayrshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressSite To North East Of Castlehill Farm, Stevenston, Ayrshire, KA13 6TTDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (abandoned)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date16 Oct 2015 (permit 15/00469/PP, Town and Country Planning Act, issued by North Ayrshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date26 Aug 2015 (reference 15/00469/PP, planning authority North Ayrshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date16 Oct 2015 (granted, reference 15/00469/PP, planning authority North Ayrshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSBC RenewablesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area12.3 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates55.6560, -4.7262DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority North Ayrshire, reference 15/00469/PP)
  2. Permit applied for (planning authority North Ayrshire, reference 15/00469/PP)

How it compares

Castlehill Solar Farm is the 755th-largest of 1,196 power plants in Scotland and the 2,742nd-largest of 5,050 in the United Kingdom by capacity; its 5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland755th of 1,19634,589 MW<0.1%
United Kingdom2,742nd of 5,050115,622 MW<0.1%
All power plants in our data8,380th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 22 substations, 14 grid connections (8 operating, 81.7 MW) and 4 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Ballochmartin Farm grid connectionGrid connection3.5 MWPlanned17 km
Bruchag PrimarySubstation——22 km
Brodick PrimarySubstation——28 km
Rothesay PrimarySubstation——29 km
Glenkiln Farm grid connectionGrid connection4 MWPlanned30 km
iomart Glasgow Data CentreData center——35 km
Verizon Glasgow GLSGGBData center——36 km
DataVita DV2Data center——37 km
45MW Battery grid connectionGrid connection52.7 MWPlanned38 km

Operator and place

More from SBC Renewables

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page