Power plant · Orkney Islands, Scotland, United Kingdom

Bu Wind Farm Repowering

Bu Wind Farm Repowering is a cancelled power plant in Orkney Islands, Scotland, United Kingdom, with 2.6 MW of capacity, operated by Scottish and Southern Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationOrkney Islands (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressStronsay, Orkney, Islands, KW17DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (abandoned)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date12 Apr 2013 (permit 12/725/TPP, Town and Country Planning Act, issued by Orkney Islands)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date6 Nov 2012 (reference 12/725/TPP, planning authority Orkney Islands)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 Apr 2013 (granted, reference 12/725/TPP, planning authority Orkney Islands)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorScottish and Southern Energy (Scottish and Southern Energy (SSE))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.6 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units3 units (0.85 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates59.0840, -2.6571DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Orkney Islands, reference 12/725/TPP)
  2. Permit applied for (planning authority Orkney Islands, reference 12/725/TPP)

How it compares

Bu Wind Farm Repowering is the 915th-largest of 1,196 power plants in Scotland and the 3,901st-largest of 5,050 in the United Kingdom by capacity; its 2.6 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland915th of 1,19634,589 MW<0.1%
United Kingdom3,901st of 5,050115,622 MW<0.1%
All power plants in our data9,955th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 30 grid connections (16 operating, 63.1 MW) and 15 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Stronsay PrimarySubstation——5.4 km
Hydro 3.8 MW grid connection at Eday Tidal StreamGrid connection3.8 MWOperating11 km
Eday Tidal Developments grid connectionGrid connection4.8 MWPlanned11 km
4.8MW TIDAL grid connectionGrid connection4.8 MWPlanned11 km
Eday Tidal PrimarySubstation——12 km
Eday PrimarySubstation——13 km

Operator and place

More from Scottish and Southern Energy

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page