Power plant · Highland, Scotland, United Kingdom

Blackpark House - Battery Storage

Blackpark House - Battery Storage is a permitted power plant in Highland, Scotland, United Kingdom, with 30 MW of capacity, operated by Anesco.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationHighland (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressSouth Of Blackpark House Nairn, IV12 5HYDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date14 Oct 2025 (permit 24/05019/FUL, Town and Country Planning Act, issued by Highland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date16 Dec 2024 (ref. 24/05019/FUL, Highland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date14 Oct 2025 (granted, ref. 24/05019/FUL, Highland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorAnescoDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity30 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBatteryDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.5681, -3.8116DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Blackpark House - Battery Storage is the 501st-largest of 872 power plants planned, permitted or under construction in Scotland and the 1,569th-largest of 3,222 in the United Kingdom by capacity; its 30 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland501st of 87299,272 MW<0.1%
United Kingdom1,569th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data2,981st of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 64 substations and 48 grid connections (19 operating, 526 MW), measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Blackpark Farm grid connectionGrid connection50 MWPlanned0.3 km
Nairn BESS grid connectionGrid connection29.4 MWPlanned0.3 km
Newton of Park BESS 2 grid connectionGrid connection52.7 MWPlanned0.5 km
Nairn GSPSubstation——2.4 km
Nairn Central PrimarySubstation——3.7 km
Lethen PrimarySubstation——3.8 km

Operator and place

Grid connections attached to this power plant

More from Anesco

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page