Power plant · Fife, Scotland, United Kingdom

Ballingall Farm, Leslie - Battery Energy Storage System

Ballingall Farm, Leslie - Battery Energy Storage System is a permitted power plant in Fife, Scotland, United Kingdom, with 43 MW of capacity, operated by EcoDev Group Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationFife (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressBallingall Farm, Leslie, Glenrothes, KY6 3HDDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date14 Sept 2023 (permit 23/00971/FULL, Town and Country Planning Act, issued by Fife)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date12 May 2023 (reference 23/00971/FULL, planning authority Fife)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date14 Sept 2023 (granted, reference 23/00971/FULL, planning authority Fife)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorEcoDev Group LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity43 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.2147, -3.2086DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Fife, reference 23/00971/FULL)
  2. Permit applied for (planning authority Fife, reference 23/00971/FULL)

How it compares

Ballingall Farm, Leslie - Battery Energy Storage System is the 435th-largest of 872 power plants planned, permitted or under construction in Scotland and the 1,315th-largest of 3,222 in the United Kingdom by capacity; its 43 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland435th of 87299,272 MW<0.1%
United Kingdom1,315th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data2,478th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 69 grid connections (21 operating, 370 MW), 52 substations and 9 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Binn Farm Glenfarg grid connectionGrid connection30 MWPlanned9.1 km
Binn Farm Wind Farm grid connectionGrid connection6.7 MWOperating13 km
Binn Farm - Wind grid connectionGrid connection9.9 MWPlanned13 km
Milnathort PrimarySubstation——13 km
Abernethy GSPSubstation——15 km
Abernethy PrimarySubstation——15 km
Pulsant Edinburgh SC-1Data center——32 km
Pulsant Edinburgh South Gyle SC-1Data center——32 km
Lloyds Banking Group data center, ScotlandData center——32 km

Operator and place

More from EcoDev Group Limited

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page