Power plant · South Kesteven, England, United Kingdom

Washdyke Farm, Billingborough Road - Solar farm

Washdyke Farm, Billingborough Road - Solar farm is a permitted solar power plant in South Kesteven, England, United Kingdom, with 27 MW of capacity, operated by GS Ignis Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Kesteven (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressWashdyke Farm, Billingborough Road, Folkingham, Sleaford, NG34 0EZDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date23 Apr 2024 (permit S23/0511, Town and Country Planning Act, issued by South Kesteven)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date27 Mar 2023 (reference S23/0511, planning authority South Kesteven)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date28 Jul 2023 (refused, reference S23/0511, planning authority South Kesteven)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date23 Apr 2024 (appeal granted, reference S23/0511, planning authority South Kesteven)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date23 Apr 2024 (appeal refused, reference S23/0511, planning authority South Kesteven)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date23 Apr 2024 (granted, reference S23/0511, planning authority South Kesteven)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorGS Ignis Limited (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity27 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area26 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.8921, -0.3889DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (appeal granted, planning authority South Kesteven, reference S23/0511)
  2. Permit refused (appeal refused, planning authority South Kesteven, reference S23/0511)
  3. Permit granted (planning authority South Kesteven, reference S23/0511)
  4. Permit refused (planning authority South Kesteven, reference S23/0511)
  5. Permit applied for (planning authority South Kesteven, reference S23/0511)

How it compares

Washdyke Farm, Billingborough Road - Solar farm is the 887th-largest of 1,650 power plants planned, permitted or under construction in England and the 1,445th-largest of 2,548 in the United Kingdom by capacity; its 27 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England887th of 1,650171,264 MW<0.1%
United Kingdom1,445th of 2,548279,068 MW<0.1%
All power plants planned, permitted or under construction in our data3,057th of 5,799657,076 MW<0.1%

Nearby

Within 50 km of this power plant: 4 data centers, 3 transmission lines and 2 grid connections (4.7 MW), measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Triton Knoll Electrical SystemTransmission line—Permitted12 km
Eastern Green Link 3 and Eastern Green Link 4Transmission line—Planned22 km
Digital Space DC - NewarkData center——34 km
Data center, England (OSM way 87850427)Data center——38 km
Weston Marsh to East LeicestershireTransmission line—Planned40 km
The Horizon CentreData center——45 km
Hall Water Treatment Works grid connectionGrid connection1.6 MWOperating47 km
Newton on Trent Water Works grid connectionGrid connection3.1 MWOperating48 km

Operator and place

Other power plants in England

All 5872 power plants in England, United Kingdom