Power plant · South Derbyshire, England, United Kingdom

Toyota Solar Farm - Solar Farm

Toyota Solar Farm - Solar Farm is a planned power plant in South Derbyshire, England, United Kingdom, with 16 MW of capacity, operated by Toyota Motor Manufacturing UK Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Derbyshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressToyota Manufacturing Uk, Derby, DE1 9TADESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date8 Aug 2025 (reference DMPA/2025/1001, planning authority South Derbyshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorToyota Motor Manufacturing UK LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity16 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area23 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.8738, -1.5651DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit applied for (planning authority South Derbyshire, reference DMPA/2025/1001)

How it compares

Toyota Solar Farm - Solar Farm is the 1,324th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,070th-largest of 3,222 in the United Kingdom by capacity; its 16 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,324th of 2,174185,888 MW<0.1%
United Kingdom2,070th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data4,369th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 8 data centers, 7 grid connections (4 operating, 60 MW), 5 substations and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Chesterfield to WillingtonTransmission line—Planned19 km
nLighten NottinghamData center——28 km
ExperianData center——28 km
Data center, England (OSM way 710050084)Data center——39 km
Weston Marsh to East LeicestershireTransmission line—Planned42 km
DronfieldSubstation——48 km
Ashwood DaleSubstation——48 km
Waterswallows 1 Battery grid connectionGrid connection14 MWOperating49 km
Buxton 1 Battery grid connectionGrid connection16 MWOperating49 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom