Power plant · Cotswold, England, United Kingdom

The Rainbows Solar Farm

The Rainbows Solar Farm is a power plant in Cotswold, England, United Kingdom, with 4 MW of capacity, operated by Innogy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCotswold (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressThe North Of The Byre, Badsey Lane, Willersey, GloucestershireDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2014DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date13 Jun 2013 (permit 13/00578/FUL, Town and Country Planning Act, issued by Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date12 Feb 2013 (reference 13/00578/FUL, planning authority Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date13 Jun 2013 (granted, reference 13/00578/FUL, planning authority Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date13 Jun 2013 (appeal granted, reference 13/00578/FUL, planning authority Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date25 Mar 2013 (refused, reference 13/00578/FUL, planning authority Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorInnogy (Innogy (previously BELECTRIC Solar))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity4 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area17.9 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.0707, -1.8581DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Cotswold, reference 13/00578/FUL)
  3. Permit granted (appeal granted, planning authority Cotswold, reference 13/00578/FUL)
  4. Permit refused (planning authority Cotswold, reference 13/00578/FUL)
  5. Permit applied for (planning authority Cotswold, reference 13/00578/FUL)

How it compares

The Rainbows Solar Farm is the 2,350th-largest of 3,430 power plants in England and the 3,494th-largest of 5,050 in the United Kingdom by capacity; its 4 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England2,350th of 3,43071,965 MW<0.1%
United Kingdom3,494th of 5,050115,622 MW<0.1%
All power plants in our data9,276th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 49 grid connections (23 operating, 296 MW), 28 substations and 3 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Shipton Oliffe PrimarySubstation——23 km
Rissington PrimarySubstation——24 km
Bledington PrimarySubstation——25 km
Ionos data center, EnglandData center——25 km
Evoque Data Center SolutionsData center——27 km
Tinsley Farm grid connectionGrid connection5 MWPlanned35 km
Southill PV grid connectionGrid connection4.09 MWOperating35 km
Agrivert Limited grid connectionGrid connection2.26 MWOperating36 km
DXC TechnologyData center——48 km

Operator and place

More from Innogy

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page