Power plant · Fenland, England, United Kingdom

The Drove, Pondersbridge - Anaerobic Digestion Plant

The Drove, Pondersbridge - Anaerobic Digestion Plant is a permitted power plant in Fenland, England, United Kingdom, with 6.8 MW of capacity, operated by Collmart Growers Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationFenland (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressCollmart Growers Limited The Drove Pondersbridge Huntingdon, PE26 2TPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Sept 2023 (permit 22/01107/FUL, Town and Country Planning Act, issued by Huntingdonshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date17 May 2022 (reference 22/01107/FUL, planning authority Huntingdonshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Sept 2023 (granted, reference 22/01107/FUL, planning authority Huntingdonshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorCollmart Growers LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity6.8 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyAnaerobic DigestionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.5127, -0.1427DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Huntingdonshire, reference 22/01107/FUL)
  2. Permit applied for (planning authority Huntingdonshire, reference 22/01107/FUL)

How it compares

The Drove, Pondersbridge - Anaerobic Digestion Plant is the 1,565th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,420th-largest of 3,222 in the United Kingdom by capacity; its 6.8 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,565th of 2,174185,888 MW<0.1%
United Kingdom2,420th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data5,534th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 7 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 5, up to 3 per kind.

NameKindSizeStatusDistance
Data center, England (OSM way 87850427)Data center——9.5 km
Positive ParkData center——16 km
The Horizon CentreData center——34 km
Kings Lynn B Connection ProjectTransmission line—Permitted42 km
Triton Knoll Electrical SystemTransmission line—Permitted47 km

Operator and place

Other power plants in England