Power plant · East Riding of Yorkshire, England, United Kingdom

Tedder Hill Wind cluster

Tedder Hill Wind cluster is a power plant in East Riding of Yorkshire, England, United Kingdom, with 7.5 MW of capacity, operated by Ventient.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEast Riding of Yorkshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Addressnear Roos, East Riding of YorkshireDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2013DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date28 Jan 2010 (permit 06/03729/STPLF, Town and Country Planning Act, issued by East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date11 May 2006 (ref. 06/03729/STPLF, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date28 Jan 2010 (appeal granted, ref. 06/03729/STPLF, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 Sept 2008 (refused, ref. 06/03729/STPLF, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date28 Jan 2010 (granted, ref. 06/03729/STPLF, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorVentientDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity7.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units3 unitsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.7531, -0.0231DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Tedder Hill Wind cluster is the 1,425th-largest of 3,430 power plants in England and the 2,284th-largest of 5,050 in the United Kingdom by capacity; its 7.5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,425th of 3,43071,985 MW<0.1%
United Kingdom2,284th of 5,050115,642 MW<0.1%
All power plants in our data7,732nd of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 06/03729/STPLF
  2. Started operating

Nearby

Within 50 km of this power plant: 195 grid connections (100 operating, 1,592 MW), 94 substations, 1 CO2 emitter and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Wind 17.1 MW grid connection at Roos WindfarmGrid connection17.1 MWOperating1.5 km
Wind 6.555 MW grid connection at WithernseaGrid connection6.56 MWOperating2.3 km
WithernseaSubstation——4.5 km
Burton PidseaSubstation——5.3 km
Solar 4.75 MW grid connection at Patrington RoadGrid connection4.75 MWOperating6.6 km
Patrington RoadSubstation——6.7 km
Aldbrough Hydrogen StorageCO2 emitter—Planned7.3 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled26 km