Power plant · Dorset, England, United Kingdom

Tecan Way, Granby Industrial Estate - Solar Photo Voltaic Panels

Tecan Way, Granby Industrial Estate - Solar Photo Voltaic Panels is a cancelled solar power plant in Dorset, England, United Kingdom, with 1 MW of capacity, operated by P L Cane Investments Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationDorset (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Address1 Tecan Way, Granby Industrial Estate, Chickerell, DT4 9TUDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission granted, permission expired)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date9 Jun 2023 (permit P/PASO/2023/02526, Town and Country Planning Act, issued by Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date28 Apr 2023 (reference P/PASO/2023/02526, planning authority Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date9 Jun 2023 (granted, reference P/PASO/2023/02526, planning authority Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorP L Cane Investments Limited (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.6124, -2.4819DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Dorset, reference P/PASO/2023/02526)
  2. Permit applied for (planning authority Dorset, reference P/PASO/2023/02526)

How it compares

Tecan Way, Granby Industrial Estate - Solar Photo Voltaic Panels was cancelled before it was built: it is not ranked among the power plants that run, and its 1 MW is not counted in their totals.

Nearby

Within 50 km of this power plant: 96 grid connections (60 operating, 498 MW), 69 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Chickerell GSPSubstation——1.3 km
Chickerell BSPSubstation——1.3 km
Chickerell PrimarySubstation——1.3 km
49.9MW BESS grid connectionGrid connection49.9 MWPlanned1.7 km
Chickerell 132 KV S/Stn grid connectionGrid connection47.4 MWOperating1.8 km
Chickerell grid connectionGrid connection4.77 MWOperating2.3 km
Data Vault - Bournemouth BCP01Data center——44 km

Operator and place

Other power plants in England

All 5872 power plants in England, United Kingdom