Power plant · South Cambridgeshire, England, United Kingdom

Streetly Hall Farm, West Wickham - Anaerobic Digestion Renewable Energy Facility

Streetly Hall Farm, West Wickham - Anaerobic Digestion Renewable Energy Facility is a permitted power plant in South Cambridgeshire, England, United Kingdom, with 7 MW of capacity, operated by Streetly Hall Farm.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Cambridgeshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressStreetly Hall Farm, West Wickham - Anaerobic Digestion Renewable Energy Facility, CB21 4RPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Jul 2024 (permit CCC/23/110/FUL, Town and Country Planning Act, issued by South Cambridgeshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date10 Oct 2023 (reference CCC/23/110/FUL, planning authority South Cambridgeshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Jul 2024 (granted, reference CCC/23/110/FUL, planning authority South Cambridgeshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorStreetly Hall FarmDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity7 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyAnaerobic DigestionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.1084, 0.3600DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority South Cambridgeshire, reference CCC/23/110/FUL)
  2. Permit applied for (planning authority South Cambridgeshire, reference CCC/23/110/FUL)

How it compares

Streetly Hall Farm, West Wickham - Anaerobic Digestion Renewable Energy Facility is the 1,553rd-largest of 2,174 power plants planned, permitted or under construction in England and the 2,403rd-largest of 3,222 in the United Kingdom by capacity; its 7 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,553rd of 2,174185,888 MW<0.1%
United Kingdom2,403rd of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data5,515th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 6 data centers, 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 5, up to 3 per kind.

NameKindSizeStatusDistance
Redcentric CambridgeData center——20 km
West Cambridge Data CentreData center——22 km
US Air Force data center, BrandonData center——35 km
Bramford to TwinsteadTransmission line—Permitted36 km
NVIDIA Cambridge-1AI supercomputer202 H100eOperating41 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page