Power plant · Torridge, England, United Kingdom

Stoneworthy - Battery Energy Storage System

Stoneworthy - Battery Energy Storage System is a permitted power plant in Torridge, England, United Kingdom, with 49.9 MW of capacity, operated by RES Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTorridge (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressNear Lower Hopworthy, Pyworthy, EX22 6LADESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date3 Jul 2025 (permit 1/0514/2024/FULM, Town and Country Planning Act, issued by Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date3 Jun 2024 (reference 1/0514/2024/FULM, planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date3 Jul 2025 (granted, reference 1/0514/2024/FULM, planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date3 Jul 2025 (appeal granted, reference 1/0514/2024/FULM, planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date20 Sept 2024 (refused, reference 1/0514/2024/FULM, planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorRES LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.7946, -4.3958DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (appeal granted, planning authority Torridge, reference 1/0514/2024/FULM)
  2. Permit granted (planning authority Torridge, reference 1/0514/2024/FULM)
  3. Permit refused (planning authority Torridge, reference 1/0514/2024/FULM)
  4. Permit applied for (planning authority Torridge, reference 1/0514/2024/FULM)

How it compares

Stoneworthy - Battery Energy Storage System is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174185,888 MW<0.1%
United Kingdom886th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 1 data center and 1 mine, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Data center, England (OSM way 164113041)Data center——15 km
Tungsten WestMine——50 km

Operator and place

More from RES Limited

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page