Power plant · Chelmsford, England, United Kingdom

Southlands Solar Farm & Battery Storage

Southlands Solar Farm & Battery Storage is a permitted power plant in Chelmsford, England, United Kingdom, with 24.6 MW of capacity, operated by Enso Green Holdings Limited and Cero Generation.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationChelmsford (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand South Of Southlands Cottages Runwell Road Runwell, SS11 7ABDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date26 Nov 2024 (permit 23/00532/FUL, Town and Country Planning Act, issued by Chelmsford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date6 Apr 2023 (reference 23/00532/FUL, planning authority Chelmsford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date26 Nov 2024 (granted, reference 23/00532/FUL, planning authority Chelmsford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date6 Dec 2023 (refused, reference 23/00532/FUL, planning authority Chelmsford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date26 Nov 2024 (appeal granted, reference 23/00532/FUL, planning authority Chelmsford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorEnso Green Holdings Limited (Enso Green Holdings Limited / Cero Generation)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorCero Generation (Enso Green Holdings Limited / Cero Generation)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity24.6 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area66.1 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.6199, 0.5499DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Chelmsford, reference 23/00532/FUL)
  2. Permit granted (appeal granted, planning authority Chelmsford, reference 23/00532/FUL)
  3. Permit refused (planning authority Chelmsford, reference 23/00532/FUL)
  4. Permit applied for (planning authority Chelmsford, reference 23/00532/FUL)

How it compares

Southlands Solar Farm & Battery Storage is the 1,148th-largest of 2,174 power plants planned, permitted or under construction in England and the 1,797th-largest of 3,222 in the United Kingdom by capacity; its 24.6 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,148th of 2,174185,888 MW<0.1%
United Kingdom1,797th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data3,446th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 51 data centers (1 operating, 88 MW), 2 grid connections (1 operating, 6.94 MW), 2 transmission lines and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Imperium 315Data center——5.8 km
CityFibre CabinetsData center——8.6 km
Fujitsu Data CentreData center——25 km
NVIDIA Cambridge-1AI supercomputer202 H100eOperating33 km
Solar 6.935 MW grid connection at Maiden NewtonGrid connection6.94 MWOperating36 km
North London (Electricity Line) ReinforcementTransmission line—Permitted41 km
Tertiary Study grid connectionGrid connection57 MWPlanned46 km
Bramford to TwinsteadTransmission line—Permitted48 km

Operators and place

More from Enso Green Holdings Limited

Other power plants in England

All 5809 power plants in England, United Kingdom