Power plant · Rushcliffe, England, United Kingdom

Sharpley Hill Solar Farm

Sharpley Hill Solar Farm is a permitted power plant in Rushcliffe, England, United Kingdom, with 4.2 MW of capacity, operated by Opdenergy UK 2 Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRushcliffe (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressR/O Rushcliffe Grove, East Leake, Nottingham, NG12DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date2 Dec 2021 (permit 21/00703/FUL, Town and Country Planning Act, issued by Rushcliffe)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date4 Mar 2021 (reference 21/00703/FUL, planning authority Rushcliffe)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date2 Dec 2021 (granted, reference 21/00703/FUL, planning authority Rushcliffe)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorOpdenergy UK 2 LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity4.2 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area10.8 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.8466, -1.1686DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Sharpley Hill Solar Farm is the 1,697th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,597th-largest of 3,222 in the United Kingdom by capacity; its 4.2 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,697th of 2,174186,088 MW<0.1%
United Kingdom2,597th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data5,741st of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 6 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 5, up to 3 per kind.

NameKindSizeStatusDistance
ExperianData center——4.0 km
Weston Marsh to East LeicestershireTransmission line—Planned15 km
nLighten NottinghamData center——18 km
Chesterfield to WillingtonTransmission line—Planned28 km
Santander data center, EnglandData center——29 km

Operator and place

More from Opdenergy UK 2 Limited

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page