Power plant · Torridge, England, United Kingdom

Pitworthy Farm Solar Park

Pitworthy Farm Solar Park is a power plant in Torridge, England, United Kingdom, with 15.6 MW of capacity, operated by Hive Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTorridge (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressPitworthy Farm Pancrasweek Holsworthy Devon, EX22 7JTDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2014DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date4 Jul 2013 (permit 1/0833/2012/FULM, Town and Country Planning Act, issued by Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date18 Oct 2012 (reference 1/0833/2012/FULM, planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date4 Jul 2013 (granted, reference 1/0833/2012/FULM, planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorHive EnergyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity15.6 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.8217, -4.4254DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Pitworthy Farm Solar Park is the 771st-largest of 3,430 power plants in England and the 1,381st-largest of 5,050 in the United Kingdom by capacity; its 15.6 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England771st of 3,43071,985 MW<0.1%
United Kingdom1,381st of 5,050115,642 MW<0.1%
All power plants in our data4,980th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 1/0833/2012/FULM
  2. Started operating

Nearby

Within 50 km of this power plant: 134 grid connections and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.

NameKindSizeStatusDistance
Holsworthy Pitworthy Solar Farm grid connectionGrid connection——0.5 km
Norton Farm Solar Farm grid connectionGrid connection——2.4 km
Hoppaworthy Energy Park grid connectionGrid connection——3.2 km
Data center, England (OSM way 164113041)Data center——11 km

Operator and place

More from Hive Energy

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page