Power plant · East Riding of Yorkshire, England, United Kingdom
Outstray Farm Wind Project
Outstray Farm Wind Project is a cancelled power plant in East Riding of Yorkshire, England, United Kingdom, with 1.8 MW of capacity, operated by Farm Energy.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | East Riding of Yorkshire (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Sunk Island Humberside | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Cancelled (planning application withdrawn) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 18 Jun 1999 (reference 362/10019, planning authority East Riding of Yorkshire) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 5 Aug 2005 (withdrawn, reference 362/10019, planning authority East Riding of Yorkshire) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Farm Energy (Farm Energy (The Wind Company Ltd)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 1.8 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 53.6487, 0.0141 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchHow it compares
Outstray Farm Wind Project is the 2,958th-largest of 3,430 power plants in England and the 4,399th-largest of 5,050 in the United Kingdom by capacity; its 1.8 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 2,958th of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 4,399th of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 10,752nd of 12,008 | 1,173,302 MW | <0.1% |
Nearby
Within 50 km of this power plant: 201 grid connections (100 operating, 1,563 MW), 92 substations, 3 transmission lines and 1 gas storage facility, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Easington | Substation | — | — | 6.8 km |
| Easington (Centrica Storage Ltd) Intermittent Generation grid connection | Grid connection | 3.6 MW | Operating | 7.1 km |
| Gas 12 MW grid connection at Easington | Grid connection | 12 MW | Operating | 7.1 km |
| Generation 2.5 MW grid connection at Easington | Grid connection | 2.5 MW | Operating | 7.1 km |
| Patrington Road | Substation | — | — | 7.8 km |
| Withernsea | Substation | — | — | 8.7 km |
| Aldbrough Hydrogen Storage | Gas storage facility | — | Planned | 19 km |
| Continental Link Multi-Purpose Interconnector | Transmission line | — | Cancelled | 33 km |
| Grimsby to Walpole | Transmission line | — | Planned | 42 km |
Operator and place
More from Farm Energy
- Leys Lane - Solar Panels49.9 MW · planned
- Ware Solar Park - Solar Farm & Battery Energy Storage24 MW · permitted
- Barnard Castle - Solar Farm & Battery Storage System16 MW · permitted
- Pentland Road Wind Farm13.8 MW
- Dunlop Place, Meadowhead Industrial Estate - Wind turbine7 MW · planned
- Ware Solar Park - Solar Farm & Battery Energy Storage5 MW · permitted
- Barkin House Wind Farm4.7 MW
- Barnard Castle - Solar Farm & Battery Storage System4 MW · permitted
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.