Power plant · Torridge, England, United Kingdom

North Tamar Environ Project - Holsworthy (Farm AD)

North Tamar Environ Project - Holsworthy (Farm AD) is a biomass power plant in Torridge, England, United Kingdom, with 1.4 MW of capacity, operated by Holsworthy Biogas Company.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTorridge (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand north-east of Higher Manworth Holsworthy , DevonDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2002DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date14 May 1999 (Town and Country Planning Act, issued by Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date21 Dec 1998 (planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date14 May 1999 (granted, planning authority Torridge)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorHolsworthy Biogas Company (Holsworthy Biogas Company ( North Tamar Business Network))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.4 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyAnaerobic DigestionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.8283, -4.3498DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Torridge)
  3. Permit applied for (planning authority Torridge)

How it compares

North Tamar Environ Project - Holsworthy (Farm AD) is the 3,682nd-largest of 4,035 power plants in England and the 5,376th-largest of 5,834 in the United Kingdom by capacity; its 1.4 MW is <0.1% of the 200,500 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England3,682nd of 4,035134,434 MW<0.1%
United Kingdom5,376th of 5,834200,500 MW<0.1%
All power plants in our data14,980th of 15,8001,923,633 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 1 data center, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Data center, England (OSM way 164113041)Data center——16 km

Operator and place

Other power plants in England

All 5872 power plants in England, United Kingdom

Data on this page