Power plant · Broxtowe, England, United Kingdom

Moto Hospitality, Trowell Services Area North - Solar Farm & Battery

Moto Hospitality, Trowell Services Area North - Solar Farm & Battery is a planned power plant in Broxtowe, England, United Kingdom, with 16.1 MW of capacity, operated by Moto Hospitality Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBroxtowe (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressThe Ne/O Moto Hospitality Limited, Trowell Services Area North M1 Trowell Services Northbound Off Slip, Trowell, Nottingham, NG9 3PLDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date26 Feb 2025 (reference 25/00147/FUL, planning authority Broxtowe)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorMoto Hospitality LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity16.1 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area12.4 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.9623, -1.2650DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit applied for (planning authority Broxtowe, reference 25/00147/FUL)

How it compares

Moto Hospitality, Trowell Services Area North - Solar Farm & Battery is the 1,323rd-largest of 2,174 power plants planned, permitted or under construction in England and the 2,069th-largest of 3,222 in the United Kingdom by capacity; its 16.1 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,323rd of 2,174185,888 MW<0.1%
United Kingdom2,069th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data4,366th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 41 substations, 29 grid connections (14 operating, 172 MW), 8 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
nLighten NottinghamData center——6.0 km
ExperianData center——12 km
Chesterfield to WillingtonTransmission line—Planned14 km
Weston Marsh to East LeicestershireTransmission line—Planned28 km
Digital Space DC - NewarkData center——34 km
Wind 20.22 MW grid connection at Pennyhill WindfarmGrid connection20.2 MWOperating40 km
DronfieldSubstation——40 km
Kiveton ParkSubstation——41 km
Wind 4.5 MW grid connection at Kiveton ParkGrid connection4.5 MWOperating41 km