Power plant · Doncaster, England, United Kingdom

Mere Flats Solar Farm

Mere Flats Solar Farm is a planned power plant in Doncaster, England, United Kingdom, with 16 MW of capacity, operated by NextPower UK.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationDoncaster (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressMoor Lane Micklebring, S66 7RNDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 Aug 2022 (ref. 22/01978/FULM, Doncaster)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNextPower UKDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity16 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBatteryDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.4412, -1.2261DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Mere Flats Solar Farm is the 1,324th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,070th-largest of 3,222 in the United Kingdom by capacity; its 16 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,324th of 2,174186,088 MW<0.1%
United Kingdom2,070th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data4,369th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 525 grid connections (200 operating, 2,231 MW), 283 substations and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Solar 35 MW grid connection at Fordoles Farm PVGrid connection35 MWPlanned0.2 km
SilverwoodSubstation——3.5 km
Solar 7 MW grid connection at Tickhill RoadGrid connection7 MWPlanned3.9 km
Solar 7.5 MW grid connection at Maltby CollieryGrid connection7.5 MWPlanned3.9 km
Tickhill RoadSubstation——4.7 km
New Orchard LaneSubstation——4.7 km
North Humber to High MarnhamTransmission line—Planned24 km
Chesterfield to WillingtonTransmission line—Planned48 km

Operator and place

More from NextPower UK

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page