Power plant · Cornwall, England, United Kingdom
Menear Road - Solar & Battery storage
Menear Road - Solar & Battery storage is a permitted power plant in Cornwall, England, United Kingdom, with 5 MW of capacity, operated by Anesco.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Cornwall (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | E/O Menear Farm Menear Road St Austell, PL25 3JT | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (appeal granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 13 Feb 2026 (permit PA23/09532, Town and Country Planning Act, issued by Cornwall) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 5 Mar 2024 (reference PA23/09532, planning authority Cornwall) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 13 Feb 2026 (granted, reference PA23/09532, planning authority Cornwall) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 13 Feb 2026 (appeal granted, reference PA23/09532, planning authority Cornwall) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 23 Apr 2025 (refused, reference PA23/09532, planning authority Cornwall) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Anesco | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 5 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery (co-located with re) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 50.3570, -4.7614 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchHow it compares
Menear Road - Solar & Battery storage is the 1,613th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,484th-largest of 3,222 in the United Kingdom by capacity; its 5 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,613th of 2,174 | 186,088 MW | <0.1% |
| United Kingdom | 2,484th of 3,222 | 300,661 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 5,616th of 6,455 | 664,240 MW | <0.1% |
Nearby
Within 50 km of this power plant: 159 grid connections, measured from the coordinates in the facts above. The table shows the nearest 3.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| The Eden Project grid connection | Grid connection | — | — | 1.4 km |
| West Carclaze Mica Dam, West Carclaze grid connection | Grid connection | — | — | 1.7 km |
| Land at grid connection | Grid connection | — | — | 1.9 km |
Operator and place
More from Anesco
- Persley BESS - Battery Storage70.1 MW · permitted
- Marston Sewerage Pumping Station, Bodymoor Heath Lane - Battery Storage50 MW · planned
- Newton Wood Farm49.9 MW · permitted
- Rothienorman - Battery Storage49.9 MW · permitted
- Turf Carr Solar Farm49.9 MW · permitted
- Overton Grange, Overton Road - Solar Farm Battery Energy Storage49.9 MW · planned
- Low Farm Solar Farm49.9 MW · under construction
- Brentwood nergy Storage System49.9 MW · permitted
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.