Power plant · Wealden, England, United Kingdom

Lower Claverham Farm & Mount Pleasant Farm, Berwick - Solar Farm

Lower Claverham Farm & Mount Pleasant Farm, Berwick - Solar Farm is a cancelled power plant in Wealden, England, United Kingdom, with 49.9 MW of capacity, operated by Scottish Power Renewables.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWealden (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressN/O Lower Claverham Farm, Berwick, Chalvington, Polegate, BN26 6TJDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date19 Jan 2022 (reference WD/2021/2617/MEA, planning authority Wealden)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date24 Mar 2023 (refused, reference WD/2021/2617/MEA, planning authority Wealden)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorScottish Power RenewablesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area81.5 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.8626, 0.1796DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority Wealden, reference WD/2021/2617/MEA)
  2. Permit applied for (planning authority Wealden, reference WD/2021/2617/MEA)

How it compares

Lower Claverham Farm & Mount Pleasant Farm, Berwick - Solar Farm is the 175th-largest of 3,430 power plants in England and the 362nd-largest of 5,050 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England175th of 3,43071,965 MW<0.1%
United Kingdom362nd of 5,050115,622 MW<0.1%
All power plants in our data1,865th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 9 data centers, 2 substations and 1 grid connection (3.91 MW), measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Goldman Sachs data center, East GrinsteadData center——34 km
Digital Realty LGW15Data center——39 km
Digital Realty LGW16Data center——39 km
Five Oaks PrimarySubstation——47 km
Solar 3.905 MW grid connection at Five Oaks Farm PVGrid connection3.91 MWOperating48 km
Billingshurst PrimarySubstation——48 km

Operator and place

More from Scottish Power Renewables

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page