Linton Court Farm, Highnam - Battery storage is a permitted power plant in Tewkesbury, England, United Kingdom, with 99.9 MW of capacity, operated by STOR 136 Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTewkesbury (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLinton Court Farm, Highnam, GL2 8DFDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date21 Aug 2023 (permit 22/01374/FUL, Town and Country Planning Act, issued by Tewkesbury)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date20 Dec 2022 (reference 22/01374/FUL, planning authority Tewkesbury)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 Aug 2023 (granted, reference 22/01374/FUL, planning authority Tewkesbury)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSTOR 136 LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity99.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.8707, -2.2859DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Linton Court Farm, Highnam - Battery storage is the 296th-largest of 2,174 power plants planned, permitted or under construction in England and the 501st-largest of 3,222 in the United Kingdom by capacity; its 99.9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England296th of 2,174186,088 MW<0.1%
United Kingdom501st of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,415th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 68 grid connections (43 operating, 598 MW), 42 substations, 6 data centers and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
DXC TechnologyData center——14 km
Shipton Oliffe PrimarySubstation——23 km
Whiteway PrimarySubstation——27 km
Tetbury PrimarySubstation——27 km
Bathurst Estates grid connectionGrid connection49.9 MWOperating28 km
Cirencester Solar Park grid connectionGrid connection25 MWPlanned28 km
Crucis Park Estate LLP grid connectionGrid connection12.6 MWPlanned30 km
Ionos data center, EnglandData center——38 km
nLighten BristolData center——42 km