Power plant · South Derbyshire, England, United Kingdom

Land at Sunnyside Court

Land at Sunnyside Court is a cancelled power plant in South Derbyshire, England, United Kingdom, with 4.9 MW of capacity, operated by Ethical Power.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Derbyshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand at SK2821 3837, Sunnyside Court, Newhall, Swadlincote, Derbyshire, DE11 0GYDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date6 May 2015 (reference 9/2015/0124, planning authority South Derbyshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date16 Dec 2015 (refused, reference 9/2015/0124, planning authority South Derbyshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorEthical PowerDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity4.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area9.68 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.7879, -1.5740DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority South Derbyshire, reference 9/2015/0124)
  2. Permit applied for (planning authority South Derbyshire, reference 9/2015/0124)

How it compares

Land at Sunnyside Court is the 2,193rd-largest of 3,430 power plants in England and the 3,273rd-largest of 5,050 in the United Kingdom by capacity; its 4.9 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England2,193rd of 3,43071,965 MW<0.1%
United Kingdom3,273rd of 5,050115,622 MW<0.1%
All power plants in our data8,942nd of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 7 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 5, up to 3 per kind.

NameKindSizeStatusDistance
Chesterfield to WillingtonTransmission line—Planned29 km
Data center, England (OSM way 710050084)Data center——30 km
ExperianData center——31 km
Santander data center, EnglandData center——34 km
Weston Marsh to East LeicestershireTransmission line—Planned42 km

Operator and place

More from Ethical Power

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page