Power plant · Telford and Wrekin, England, United Kingdom

High Ercall Solar Farm

High Ercall Solar Farm is a cancelled power plant in Telford and Wrekin, England, United Kingdom, with 49.9 MW of capacity, operated by Assured Asset Solar 1 Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTelford and Wrekin (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressEast & South of Angel Centre, Osbaston, TF6 6QZDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission granted, permission expired)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Aug 2023 (permit TWC/2023/0064, Town and Country Planning Act, issued by Telford and Wrekin)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date26 Jan 2023 (reference TWC/2023/0064, planning authority Telford and Wrekin)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Aug 2023 (granted, reference TWC/2023/0064, planning authority Telford and Wrekin)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorAssured Asset Solar 1 Limited (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area89.5 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.7681, -2.5862DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Telford and Wrekin, reference TWC/2023/0064)
  2. Permit applied for (planning authority Telford and Wrekin, reference TWC/2023/0064)

How it compares

High Ercall Solar Farm is the 234th-largest of 3,953 power plants in England and the 447th-largest of 5,723 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 136,106 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England234th of 3,95385,679 MW<0.1%
United Kingdom447th of 5,723136,106 MW<0.1%
All power plants in our data1,950th of 12,7051,210,931 MW<0.1%

Nearby

Within 50 km of this power plant: 3 transmission lines, 3 data centers and 1 gas storage facility, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Reinforcement to North Shropshire Electricity Distribution NetworkTransmission line—Permitted22 km
Internet Central data center, EnglandData center——34 km
Mid Wales Electricity Connection (N Grid)Transmission line—Cancelled37 km
Green Gen Vyrnwy FranktonTransmission line—Planned41 km
Salinae Hydrogen Storage projectGas storage facility—Planned43 km
Hutchison 3GData center——45 km
EE Data CentreData center——46 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom