Power plant · South Holland, England, United Kingdom

Gunthorpe Road, Marsh - Solar Farm

Gunthorpe Road, Marsh - Solar Farm is a permitted solar power plant in South Holland, England, United Kingdom, with 49.9 MW of capacity, operated by Walpole Green Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Holland (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressSouth of Gunthorpe Road Walpole Marsh Wisbech, PE14 7JHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date29 Sept 2023 (permit 21/01442/FM, Town and Country Planning Act, issued by South Holland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date20 Jul 2021 (reference 21/01442/FM, planning authority South Holland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date29 Sept 2023 (granted, reference 21/01442/FM, planning authority South Holland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date29 Sept 2023 (appeal granted, reference 21/01442/FM, planning authority South Holland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date25 Feb 2022 (refused, reference 21/01442/FM, planning authority South Holland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorWalpole Green Limited (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area78.6 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.7397, 0.1861DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (appeal granted, planning authority South Holland, reference 21/01442/FM)
  2. Permit granted (planning authority South Holland, reference 21/01442/FM)
  3. Permit refused (planning authority South Holland, reference 21/01442/FM)
  4. Permit applied for (planning authority South Holland, reference 21/01442/FM)

How it compares

Gunthorpe Road, Marsh - Solar Farm is the 455th-largest of 1,651 power plants planned, permitted or under construction in England and the 801st-largest of 2,549 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 279,978 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England455th of 1,651172,174 MW<0.1%
United Kingdom801st of 2,549279,978 MW<0.1%
All power plants planned, permitted or under construction in our data1,881st of 5,782643,557 MW<0.1%

Nearby

Within 50 km of this power plant: 4 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Kings Lynn B Connection ProjectTransmission line—Permitted13 km
Longmarsh Green EnergyData center—Planned14 km
Positive ParkData center——19 km
Eastern Green Link 3 and Eastern Green Link 4Transmission line—Planned31 km
Triton Knoll Electrical SystemTransmission line—Permitted35 km
Data center, England (OSM way 87850427)Data center——37 km

Operator and place

Other power plants in England

All 5876 power plants in England, United Kingdom

Data on this page