Power plant · Winchester, England, United Kingdom

Glebe Farm, Curdridge Lane - Solar Farm

Glebe Farm, Curdridge Lane - Solar Farm is a planned power plant in Winchester, England, United Kingdom, with 10 MW of capacity, operated by Glebe Farm Energy Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWinchester (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressGlebe Farm, Curdridge Lane, Waltham Chase, Southampton, SO32 2LQDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 May 2025 (ref. 25/01050/FUL, Winchester)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorGlebe Farm Energy LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity10 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area21.5 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.9358, -1.2093DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Glebe Farm, Curdridge Lane - Solar Farm is the 1,441st-largest of 2,174 power plants planned, permitted or under construction in England and the 2,237th-largest of 3,222 in the United Kingdom by capacity; its 10 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,441st of 2,174186,088 MW<0.1%
United Kingdom2,237th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data5,307th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 252 grid connections (144 operating, 1,354 MW), 193 substations and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Glebe Farm grid connectionGrid connection10 MWPlanned0.2 km
Solar 11.4 MW grid connection at Bishops Waltham PVGrid connection11.4 MWOperating0.4 km
Waltham Chase grid connectionGrid connection2.5 MWOperating0.9 km
Bishops Waltham PrimarySubstation——1.6 km
Botley Wood BSPSubstation——5.9 km
Botley Wood GSPSubstation——5.9 km
Aquind InterconnectorTransmission line—Planned12 km

Operator and place

Grid connections attached to this power plant

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page