Power plant · Newark and Sherwood, England, United Kingdom
Fox Covert Wind Farm
Fox Covert Wind Farm is a cancelled power plant in Newark and Sherwood, England, United Kingdom, with 10 MW of capacity, operated by Wind Prospect Developments.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Newark and Sherwood (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Cotham Road, Hawton, Nottinghamshire | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Cancelled (secretary of state, refusal) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 4 Jul 2013 (reference 13/00889/FULM, planning authority Newark and Sherwood) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 30 Jun 2016 (secretary of state refused, reference 13/00889/FULM, planning authority Newark and Sherwood) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 29 Sept 2015 (appeal refused, reference 13/00889/FULM, planning authority Newark and Sherwood) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 9 Oct 2014 (refused, reference 13/00889/FULM, planning authority Newark and Sherwood) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Wind Prospect Developments | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 10 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Units | 5 units (2 MW per unit) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 53.0338, -0.8194 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Fox Covert Wind Farm is the 1,102nd-largest of 3,430 power plants in England and the 1,838th-largest of 5,050 in the United Kingdom by capacity; its 10 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,102nd of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 1,838th of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 7,057th of 12,008 | 1,173,302 MW | <0.1% |
Nearby
Within 50 km of this power plant: 337 grid connections (17 operating, 127 MW), 13 substations, 5 transmission lines and 3 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Hawton Cotham Grange PV 132KV grid connection | Grid connection | — | — | 0.4 km |
| Sovereign Property Partners LLP Stor Site grid connection | Grid connection | — | — | 1.9 km |
| Newark Power Generation Plant, Bowbridge Lane, Balderton, Newark grid connection | Grid connection | — | — | 2.0 km |
| Digital Space DC - Newark | Data center | — | — | 5.3 km |
| nLighten Nottingham | Data center | — | — | 27 km |
| Experian | Data center | — | — | 28 km |
| Weston Marsh to East Leicestershire | Transmission line | — | Planned | 28 km |
| Stow | Substation | — | — | 33 km |
| Lea Road | Substation | — | — | 40 km |
Operator and place
More from Wind Prospect Developments
- Tressady Wind Farm32.5 MW
- Burnhead26 MW
- Red Tile24 MW
- Mount Lothian Wind Farm20.7 MW
- Deeping St Nicholas Wind Farm16.4 MW
- Frandy Hill14 MW
- Thornholme Wind Farm12 MW
- Burnfoot East Wind Farm (further extension)10.8 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.