FactValueSource
LocationDorset (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressEast Chickerell Court Farm, Chickerell, Weymouth, DT3 4BGDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date27 Jan 2025 (permit P/FUL/2023/04657, Town and Country Planning Act, issued by Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date14 Aug 2023 (reference P/FUL/2023/04657, planning authority Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date27 Jan 2025 (granted, reference P/FUL/2023/04657, planning authority Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorStatera EnergyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity400 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.6288, -2.4877DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Dorset, reference P/FUL/2023/04657)
  2. Permit applied for (planning authority Dorset, reference P/FUL/2023/04657)

How it compares

East Chickerell Court Farm - Battery Energy Storage System is the 103rd-largest of 2,174 power plants planned, permitted or under construction in England and the 157th-largest of 3,222 in the United Kingdom by capacity; its 400 MW is 0.13% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England103rd of 2,174185,888 MW0.22%
United Kingdom157th of 3,222300,461 MW0.13%
All power plants planned, permitted or under construction in our data351st of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 98 grid connections (62 operating, 541 MW), 70 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Chickerell grid connectionGrid connection4.77 MWOperating0.5 km
49.9MW BESS grid connectionGrid connection49.9 MWPlanned0.6 km
Chickerell BSPSubstation——0.6 km
Chickerell PrimarySubstation——0.6 km
Chickerell GSPSubstation——0.6 km
Chickerell 132 KV S/Stn grid connectionGrid connection47.4 MWOperating0.7 km
Data Vault - Bournemouth BCP01Data center——44 km

Operator and place

More from Statera Energy

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page