Power plant · Stratford-on-Avon, England, United Kingdom

Dadglow Farm, Bishops Itchington - Battery Energy Storage System

Dadglow Farm, Bishops Itchington - Battery Energy Storage System is a cancelled power plant in Stratford-on-Avon, England, United Kingdom, with 20 MW of capacity, operated by Root Power Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationStratford-on-Avon (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressDadglow Farm Bishops Itchington, CV47 2RHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date3 Oct 2024 (reference 24/02516/FUL, planning authority Stratford-on-Avon)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date6 Feb 2025 (refused, reference 24/02516/FUL, planning authority Stratford-on-Avon)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorRoot Power Limited (Root Power (South) Limited)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity20 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.2172, -1.4218DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Dadglow Farm, Bishops Itchington - Battery Energy Storage System is the 573rd-largest of 3,430 power plants in England and the 1,079th-largest of 5,050 in the United Kingdom by capacity; its 20 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England573rd of 3,43071,985 MW<0.1%
United Kingdom1,079th of 5,050115,642 MW<0.1%
All power plants in our data3,907th of 12,0081,173,302 MW<0.1%

Nearby

Within 50 km of this power plant: 37 grid connections (17 operating, 145 MW), 23 substations and 8 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Deddington PrimarySubstation——28 km
Hill Farm PV grid connectionGrid connection4.51 MWOperating29 km
Duns TEW Solar Farm grid connectionGrid connection6 MWPlanned29 km
Spring Farm grid connectionGrid connection13.2 MWPlanned30 km
Chipping Norton PrimarySubstation——32 km
Cottisford PrimarySubstation——33 km
Evoque Data Center SolutionsData center——33 km
Hellermann Tyton DataData center——34 km
Data center, England (OSM way 710050084)Data center——36 km

Operator and place

More from Root Power Limited