Power plant · South Hams, England, United Kingdom

Coombeshead Solar Farm

Coombeshead Solar Farm is a solar power plant in South Hams, England, United Kingdom, with 8 MW of capacity, operated by Foresight.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Hams (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressCoombeshead Farm DiptfordDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2015DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date29 Aug 2014 (permit 17/0265/14/F, Town and Country Planning Act, issued by South Hams)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date31 Jan 2014 (reference 17/0265/14/F, planning authority South Hams)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date29 Aug 2014 (granted, reference 17/0265/14/F, planning authority South Hams)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorForesightDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity8 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area23.4 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.3862, -3.7641DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority South Hams, reference 17/0265/14/F)
  3. Permit applied for (planning authority South Hams, reference 17/0265/14/F)

How it compares

Coombeshead Solar Farm is the 1,732nd-largest of 4,035 power plants in England and the 2,693rd-largest of 5,834 in the United Kingdom by capacity; its 8 MW is <0.1% of the 200,500 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,732nd of 4,035134,434 MW<0.1%
United Kingdom2,693rd of 5,834200,500 MW<0.1%
All power plants in our data11,123rd of 15,8001,923,633 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 1 mine, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Tungsten WestMine——19 km

Operator and place

More from Foresight

Other power plants in England

All 5872 power plants in England, United Kingdom

Data on this page