Power plant · North Northamptonshire, England, United Kingdom

Braybrooke Village North, Harborough Road - Battery Energy Storage System

Braybrooke Village North, Harborough Road - Battery Energy Storage System is a planned battery storage plant in North Northamptonshire, England, United Kingdom, with 252 MW of capacity, operated by Elmya Energy Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNorth Northamptonshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressBraybrooke Village, North, Harborough Road, Market Harborough, LE16 8LLDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date24 Jul 2025 (reference 25/00810/FUL, planning authority North Northamptonshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorElmya Energy Limited (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity252 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.4669, -0.8908DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit applied for (planning authority North Northamptonshire, reference 25/00810/FUL)

How it compares

Braybrooke Village North, Harborough Road - Battery Energy Storage System is the 153rd-largest of 1,650 power plants planned, permitted or under construction in England and the 236th-largest of 2,548 in the United Kingdom by capacity; its 252 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England153rd of 1,650171,264 MW0.15%
United Kingdom236th of 2,548279,068 MW<0.1%
All power plants planned, permitted or under construction in our data589th of 5,799657,076 MW<0.1%

Nearby

Within 50 km of this power plant: 10 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.

NameKindSizeStatusDistance
The Horizon CentreData center——17 km
Santander data center, EnglandData center——25 km
Santander data center, EnglandData center——25 km
Weston Marsh to East LeicestershireTransmission line—Planned37 km

Operator and place

Other power plants in England

All 5872 power plants in England, United Kingdom

Data on this page