RARE CONTEXT Request research

Grid connection · England, United Kingdom

Weston Longville PV Farm grid connection

Weston Longville PV Farm grid connection is a grid connection in England, United Kingdom, with 9 MW of capacity, held by Esco NRG Ltd C/o RenEnergy Limited.

Map: where Weston Longville PV Farm grid connection lies
52.6997, 1.0879 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Weston Longville Primary 11kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusOperating (connected)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderEsco NRG Ltd C/o RenEnergy LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Attached toWeston Longville Primary 11kV (via a primary substation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity9 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date13 Feb 2014UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage11 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates52.6997, 1.0879UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Weston Longville PV Farm grid connection is the 1,923rd-largest of 3,539 grid connections in England and the 2,710th-largest of 4,870 in the United Kingdom by capacity; its 9 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,923rd of 3,539341,715 MW<0.1%
United Kingdom2,710th of 4,870467,981 MW<0.1%
All grid connections in our data6,367th of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 228 power plants (80 operating, 1,893 MW), 93 substations, 2 transmission lines and 2 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Weston Longville Primary 11kVSubstation——0.0 km
Woodforde FarmPower plant9 MWOperating0.4 km
Weston Airfield Wind TurbinesPower plant3.6 MWOperating0.7 km
The Old AirfieldPower plant5 MWOperating1.5 km
Sall 11kVSubstation——9.1 km
Sall Grid 33kVSubstation——9.2 km
Norwich to TilburyTransmission line—Planned19 km
Longmarsh Green EnergyData center—Planned48 km
Kings Lynn B Connection ProjectTransmission line—Permitted48 km

Holder, grid operator and place

Other grid connections in England

All 4837 grid connections in England, United Kingdom